Permit NumberBLD19-01705
StatusFinaled
Name SLETTEN CONSTRUCTION
Site Address 816 W BANNOCK ST
Project Name4th Floor Unit Relocation
Customer Number 
ePlanReviewYes
Description
(GARRO BUILDING - HVAC RELOCATION) ** This building is fire sprinklered to allow the 5th floor. Permit is for modifications to the HVAC system on the 4th floor of the existing historic building that totals approximately 5,900 square feet. Work to include relocation and enclosure of existing heat pump units. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. NO OCCUPANCY TO REMODELED TENANT SPACE IS ALLOWED UNDER THIS PERMIT. Relocated or future tenants must apply for building permit and receive a certificate of occupancy prior to occupying any portion of the 4th floor. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  2/13/2020 DONE
Per Dave Hannah, Finaling out permit
BLD-Final8/19/20198/19/20198/19/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Dustin Keyes
FIRE-Final Inspection8/19/20198/19/20198/19/2019APASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire exitnguisher is placed with a current inspection tag, ceiling tile on southeast side to be installed before BLD final. Final life fire safety inspection for area of work complete.

Plans are on the 4th Floor now Phone #: ###-#### Inspection requested via web by Dustin Keyes
BLD-Final8/19/20198/19/20198/19/2019ACANC
DetailsDave Hannah
Plans are on the 4th Floor now Phone #: ###-#### >> Inspection requested via web by Dustin Keyes Inspection cancelled from web by: Dustin Keyes
BLD-Final8/15/20198/16/20198/16/2019PNR
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Dustin Keyes needs fire final first
FIRE-Final Inspection8/15/20198/16/20198/16/2019AFAIL
DetailsMark Scharfen
plans not on site. Contractor did not return call.

Phone #: ###-#### Inspection requested via web by Dustin Keyes
BLD-Framing/Rough-in8/5/20198/5/20198/5/2019APASS
DetailsDave Hannah
Need inspection on soffit framing on around mechanical units. Once this is approved we will install gyp on wood framing and gyp on soffits. Phone #: ###-#### Inspection requested via web by Dustin Keyes
Issue PAID IN FULL permit  6/17/2019 DONE
Inspection Record Card- Bld  6/17/2019 DONE
Plan assigned to (JHB)5/29/20195/29/20196/13/2019 PASS
DetailsJoe Bruce
06/14 (2nd Rev) 06/04 (L1) 4th Floor Unit Relocation ePlan
Routing - PLAN CHECK6/11/2019 6/13/2019 PASS
DetailsJoe Bruce
PLANS/APPL TAKEN TO FRONT DESK  6/13/2019 DONE
Permit Ready to Issue  6/13/2019 DONE
MET DKEYES@SLETTENINC.COM
NEED
GC FORM
REVISED VALUE
Routing - MECHANICAL6/11/2019 6/12/2019 PASS
DetailsChad Schwendiman
Plan resubmittals received  6/11/2019 DONE
DetailsJoe Bruce
Route to Impact Fee Review6/3/20196/6/20196/4/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
1st review completed  6/3/2019 FAIL
DetailsJoe Bruce
Resubmittal required.
Plan resubmittals requested  6/3/2019 JHB
DetailsJoe Bruce
Routing - PLAN CHECK5/29/2019 6/3/2019 FAIL
DetailsJoe Bruce
See changemarks in ePlan.
Routing - MECHANICAL5/29/2019 5/30/2019 FAIL
DetailsChad Schwendiman
Emailed mechanical plan review comments to applicant. Change mark on plans as well
Intake Approval  5/29/2019 PASS
DetailsJavier Guzman
Intake Approval  5/21/2019 FAIL
DetailsBrian McGowan
Please provide the following information in order for your Prescreen to be approved:
1. Details on how the unit is being supported from the ceiling (show blocking as/if required).
2. The exit signs and exit lighting are not noted on GU101.
Application received  5/13/2019 DONE
Application submitted via PDS Online on May 13 2019 8:28PM