BLD-Energy code compliance | 6/3/2020 | 6/10/2020 | 6/10/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 6/3/2020 | 6/8/2020 | 6/8/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 5/12/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Wall Bracing | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brandon Shaw
|
|
|
shear // Jorge Phone #: ###-####
|
BLD-Foundation | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 4/8/2020 | 4/8/2020 | 4/8/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Inspection Record Card- Bld | | | 3/26/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/25/2020 | | DONE |
|
|
|
|
Meeting | | | 2/12/2020 | | DONE |
|
|
|
sent in request for extension
|
Extend Review Timeline | | | 10/23/2019 | | DONE |
|
|
|
1st approved 180 day extension per joe. See documents
|
Expiration Notice | 10/9/2019 | 10/30/2019 | 10/9/2019 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 6/4/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 5/16/2019 | 5/16/2019 | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
05/29 sfd L1 ePlan. 2nd review, failed planning still. 1st complete 5/29, missing shear plan, waiting for fire review
|
Routing - PLANNING | 6/4/2019 | | 6/4/2019 | | PASS |
Sue Cummings
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/4/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 5/30/2019 | | 5/30/2019 | | PASS |
Jenny Nelson
|
|
|
|
Routing - FIRE | 5/16/2019 | 5/16/2019 | 5/29/2019 | | PASS |
Lee G Meredith
|
|
|
05/29 residential eplan
Sprinklers are not required.
|
1st review completed | | | 5/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 5/29/2019 | | 5/29/2019 | | FAIL |
Sue Cummings
|
|
|
Still does not meet front setback of 20 ft. measured from back of sidewalk in this subdivision.
|
Routing - PLAN CHECK | 5/16/2019 | | 5/29/2019 | | FAIL |
Jenny Nelson
|
|
|
Need shear plan
|
Route to Impact Fee Review | 5/16/2019 | 5/19/2019 | 5/17/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/16/2019 | | 5/17/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/16/2019 | | 5/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 5/16/2019 | | 5/16/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/16/2019 | | 5/16/2019 | | FAIL |
Sue Cummings
|
|
|
Garage setback is 20 ft. from back of sidewalk not 15 ft.
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/16/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 5/16/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2019 | | DONE |
|
|
|
|
Application received | | | 5/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2019 2:29PM
|
BLD-Final | 8/12/2020 | 8/14/2020 | | A | |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Blower Door Test Results | 8/12/2020 | 8/14/2020 | | A | |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|