BLD-Final | 3/23/2020 | 3/24/2020 | 3/24/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 3/18/2020 | 3/23/2020 | 3/23/2020 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall ok all but for mec needs finaled
|
BLD-Blower Door Test Results | 3/18/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Energy code compliance | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Final | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Laz Ponce
|
BLD-Energy code compliance | 1/15/2020 | 1/21/2020 | 1/21/2020 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall ok after framing corrections are completed
|
BLD-Framing/Rough-in | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall c/n posted
|
BLD-Other | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Wall Bracing | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Disreguard previous enrty...
|
BLD-Wall Bracing | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs to be installed per manufacturers installations instructions and to be located as per plans...
|
BLD-Foundation | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 8/22/2019 | 8/22/2019 | 8/22/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 8/5/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/5/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/29/2019 | | |
|
|
|
|
Routing - FIRE | 5/16/2019 | 5/16/2019 | 5/29/2019 | | PASS |
Lee G Meredith
|
|
|
05/29-1518 S Boulder View EPlan Residential
Sprinklers not required.
|
Plan assigned to (J_N) | 5/16/2019 | 5/16/2019 | 5/29/2019 | | DONE |
Jenny Nelson
|
|
|
05/29 sfd L1 ePlan. 1st complete 5/28, waiting for fire review
|
1st review completed | | | 5/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2019 | | DONE |
Jenny Nelson
|
|
|
|
Override - Parcel Holds | | | 5/29/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 5/29/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/16/2019 | | 5/28/2019 | | PASS |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 5/16/2019 | 5/19/2019 | 5/17/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/16/2019 | | 5/17/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/16/2019 | | 5/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 5/16/2019 | | 5/16/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/16/2019 | | 5/16/2019 | | PASS |
Jeff Lowe
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/16/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 5/16/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2019 | | DONE |
|
|
|
|
Application received | | | 5/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2019 2:44PM
|