Print Statement | | | 11/8/2019 | | DONE |
|
|
|
|
First Notice | | 9/29/2019 | 10/25/2019 | | DONE |
|
|
|
mailed 11-1-19
|
BLD-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Mike Jordan
|
|
|
call 30 mins ahead - Lloyd Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Mike Jordan
|
|
|
Call 30 mins ahead- Lloyd Phone #: ###-####
|
Permanent Occupancy | | | 9/19/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/19/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Mike Jordan
|
|
|
Loyd Phone #: ###-####
|
BLD-Final | 8/20/2019 | 8/21/2019 | 8/20/2019 | A | CANC |
Mike Jordan
|
|
|
THIS was schedule on the wrong address//call 30 mins ahead for access- Lloyd Phone #: ###-####
|
FIRE-Final Inspection | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | CANC |
Troy Cobbley
|
|
|
Loyd call that this was schedule for the wrong address, cancel and reschudule for the correct address- 148 Cole// call 30 mins ahead for access- Lloyd Phone #: ###-####
|
BLD-Framing/Rough-in | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Mike Jordan
|
|
|
Call ahead // Lloyd Phone #: ###-####
|
Plan assigned to (BJM) | 6/5/2019 | 6/5/2019 | 7/30/2019 | | DONE |
Brian McGowan
|
|
|
07/17- 2nd Review Complete- Double L Construction, ePlan
|
Routing - PLAN CHECK | 7/30/2019 | | 7/30/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/30/2019 | | DONE |
Candy A. Nichols
|
|
|
met
|
Print Occupancy Form | | | 7/30/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/30/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/28/2019 | | 7/9/2019 | | FAIL |
Brian McGowan
|
|
|
Main Door ADA clearance
|
Routing - FIRE | 6/28/2019 | 6/28/2019 | 7/2/2019 | | PASS |
Mark Scharfen
|
|
|
07.03.2019-Completed fire review. Uploaded rev_fire 07.02.2019.pdf.
|
Route to Impact Fee Review | 6/25/2019 | 6/28/2019 | 6/26/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 6/25/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/5/2019 | | 6/25/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - FIRE | 6/5/2019 | 6/5/2019 | 6/19/2019 | | FAIL |
Mark Scharfen
|
|
|
06.19.2019-Completed fire review. Uploaded rev_fire 06.19.2019.pdf and emailed architect.
|
Routing - Addressing | 6/5/2019 | | 6/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/5/2019 | | 6/6/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 6/5/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by BJM
|
Intake Approval | | | 5/21/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following information for your Prescreen to be approved:
1. Please provide an As Is floor plan for the areas being modified. I think you are attempting to divide a larger space into two smaller ones.
2. A second Application must be uploaded showing the remaining space is going to be an unoccupied (vanilla) tenant space.
3. The numeral notations on the ADA Details are blackened and not legible.
4. Verify and detail whether the tenant wall being filled in is a required separation wall with a required fire rating.
|
Application received | | | 5/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 17 2019 10:22AM
|