Second Notice | | 9/28/2019 | 10/11/2019 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | | 9/9/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
BLD-Final | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Mike Jordan
|
|
|
call ahead // Jon Phone #: ###-####. Issues resolved. Ok for perm. occ.
|
Permanent Occupancy | | | 8/30/2019 | | DONE |
|
|
|
|
BLD-Final | 8/26/2019 | 8/27/2019 | 8/27/2019 | P | NR |
Mike Jordan
|
|
|
Jon Phone #: ###-####. Mech. and electrical pernits issued and finaled. Per contractor stair issue not yet resolved.
|
BLD-Final | 8/22/2019 | 8/23/2019 | 8/23/2019 | P | FAIL |
Mike Jordan
|
|
|
Jon- Phone #: ###-####. Needs to pull electrical and mech permits. West stair, last step to landing exceeds the 7 inch max riser height aloowed (8 inches). Provide city set of approved plans.
|
FIRE-Final Inspection | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Previous corrections addressed.
Jon- please go out late morning Phone #: ###-####
|
FIRE-Final Inspection | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | FAIL |
Jim Page
|
|
|
Provide fire sprinkler head under new overhead door, a permit is required for fire sprinkler modifications. Provide fire extinguisher with a current inspection tagt.Call 15 to 20 minutes ahead // John Phone #: ###-####
|
BLD-Final | 8/19/2019 | 8/20/2019 | 8/20/2019 | P | CANC |
Mike Jordan
|
|
|
Call 15 to 20 minutes ahead // John Phone #: ###-####
|
BLD-Framing/Rough-in | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | DEFR |
Mike Jordan
|
|
|
Jon Phone #: ###-####. No time. Inspection rescheduled for tomorrow in the am.
|
BLD-Conference | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | DONE |
Mike Jordan
|
|
|
PHONE CALL please for this conference- John Phone #: ###-####
|
BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | FAIL |
Mike Jordan
|
|
|
Call 20 ahead- John Phone #: ###-####. Needs to provide the city set of approved plans.
|
Issue PAID IN FULL permit | | | 6/21/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/18/2019 | | 6/19/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/19/2019 | | DONE |
|
|
|
MET erin@ekcconstruction.com
Need GC
Need Rev Val
|
Plan assigned to (M_H) | 6/3/2019 | | 6/19/2019 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 06/06 #518 L2 ePlan - Boise Rigging & Supply
|
Routing Off Site - STRUCTURAL | 5/25/2019 | | 6/18/2019 | | PASS |
Michael Hanson
|
|
|
Per ePlan approval by Chris Holladay @ AHJ engineering.
|
Route to Impact Fee Review | 6/7/2019 | 6/10/2019 | 6/12/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/12/2019 | | 6/12/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing - FIRE | 5/25/2019 | 5/25/2019 | 6/6/2019 | | PASS |
Mark Scharfen
|
|
|
06.06.2019-Completed fire review. Made notations on plans. No report needed. Passed review.
|
Routing - PLAN CHECK | 5/25/2019 | | 6/6/2019 | | FAIL |
Michael Hanson
|
|
|
Current TI requires original building plans for review. I have requested them from ADA County.
|
1st review completed | | | 6/6/2019 | | FAIL |
Michael Hanson
|
|
|
Current TI requires original building plans for review. I have requested them from ADA County. Review will commence after full orignial plans are received from ADA County.
|
Plan assigned to (JAR) | 5/25/2019 | 5/25/2019 | 6/3/2019 | | DEFR |
Julie Romig
|
|
|
06/06 - L2 Boise Rigging & Supply
|
Routing - Addressing | 5/25/2019 | | 5/29/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/25/2019 | | 5/28/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 5/25/2019 | | 5/28/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Intake Approval | | | 5/24/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/22/2019 | | FAIL |
Michael Hanson
|
|
|
Add special inspection firm to the #310 form coversheet
Upload planning and zoning letter of approval for exterior modifications
|
Application received | | | 5/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2019 2:05PM
|