Permanent Occupancy | | | 6/18/2019 | | DONE |
|
|
|
|
BLD-Final | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | PASS |
Mike Jordan
|
|
|
Janice- office opens after 9am Phone #: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Janice- office opens at 9am, please call for access Phone #: ###-####
|
FIRE-Final Inspection | 5/31/2019 | 6/4/2019 | 6/4/2019 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Janice. Signage is not ready. Phone #: ###-####
|
BLD-Final | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | NR |
Mike Jordan
|
|
|
Janice Phone #: ###-####. Fire/life/safety has failed.
|
FIRE-Final Inspection | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the ire extinguisher as discussed. Remove the thumb turn dead bolt (keyed ok) at the main exit and provide single action hardware at the main exit as per the approved plans. Janice Phone #: ###-####
|
FIRE-Final Inspection | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | FAIL |
Troy Cobbley
|
|
|
Called contact and let here know I was on the way. I waited at the building for 15 minutes after arriving and nobody showed up. I called contact5 again and let her know they would need to reschedule for a time they could be there.
Janice Phone #: ###-####
|
Plan assigned to (BJM) | 5/21/2019 | 5/21/2019 | 5/29/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2019 | | DONE |
Brian McGowan
|
|
|
|
Print Occupancy Form | | | 5/29/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/29/2019 | | DONE |
|
|
|
met
|
Telephone call | | | 5/29/2019 | | DONE |
|
|
|
Spoke with Ward to inform him the permit is ready.
|
Issue PAID IN FULL permit | | | 5/29/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/21/2019 | | 5/28/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 5/28/2019 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 5/28/2019 | | DONE |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 5/21/2019 | | 5/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 5/21/2019 | | 5/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/21/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/20/2019 | | PASS |
Brian McGowan
|
|
|
|
First Notice | | 8/11/2019 | | | |
|
|
|
|
Application received | | 5/20/2019 | | | |
|
|
|
|