Second Notice | | 11/8/2019 | 11/5/2019 | | DONE |
|
|
|
This permit finaled on the web by Scott Asin
|
First Notice | | 10/10/2019 | 10/29/2019 | | DONE |
|
|
|
Mailed 11-1
|
Permanent Occupancy | | | 9/30/2019 | | DONE |
|
|
|
|
BLD-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin. All issues have been resolved. Ok for perm occ.
|
BLD-Final | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin. Provide ADA comliant hardware on barn doors. Provide ADA compliant sink.Rfelctive surface for Mirror in restroom exceeds the 40" max height above the floor. Correction notice was issued.
|
FIRE-Final Inspection | 9/17/2019 | 9/18/2019 | 9/18/2019 | P | CANC |
Troy Cobbley
|
|
|
>> Inspection requested via web by Scott Asin Inspection cancelled from web by: Scott Asin
|
BLD-Final | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin. Noted 2 open mech. permits. mech final for today has failed.
|
FIRE-Final Inspection | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Scott Asin
|
FIRE-Final Inspection | 9/11/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Jim Page
|
|
|
Provide city approved drawings, blue prints on site are not the stamped city approved set of drawings.
documentsPhone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Energy code compliance | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin//vapor barrier repaired//
|
BLD-Energy code compliance | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin//repair vapor barrier at back wall in bathroom, repair vapor barrier at front wall//
|
BLD-Framing/Rough-in | 7/23/2019 | 7/24/2019 | 7/24/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin//trades roughs passed// ok to insulate only//replace vapor barrier//
|
Issue PAID IN FULL permit | | | 6/17/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/17/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/6/2019 | 6/9/2019 | 6/6/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 6/6/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
all met and emailed kyle@asignc.com the fees due 6-17-19 NEED
GC FORM-met
REVISED VALUE-met
MET
ACHD
|
Plan assigned to (M_H) | 5/25/2019 | | 6/6/2019 | | DONE |
Michael Hanson
|
|
|
06/06 #518 L2 ePlan - J. Oates Portrait Design
|
Routing - PLAN CHECK | 5/25/2019 | | 6/6/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing - FIRE | 5/25/2019 | 5/25/2019 | 6/5/2019 | | PASS |
Mark Scharfen
|
|
|
06.05.2019-Completed fire review. Made notations on plans. Passed review. No report.
|
Routing - Addressing | 5/25/2019 | | 5/29/2019 | | PASS |
Doug Chausow
|
|
|
Suite 110
|
Routing - PUBLIC WORKS | 5/25/2019 | | 5/28/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - MECHANICAL | 5/25/2019 | | 5/28/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 5/25/2019 | | 5/28/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 5/24/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/22/2019 | | FAIL |
Michael Hanson
|
|
|
Provide structural analysis letter for new RTU's.
|
Application received | | | 5/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2019 4:26PM
|