BLD-Final | 3/4/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Tony Young
|
|
|
Greg Phone #: ###-####
|
DOC - Permit Finaled | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Blower Door Test Results | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | DONE |
Tony Young
|
|
|
Greg Phone #: ###-####// 3,98
|
BLD-Wall Bracing | 12/31/2019 | 1/2/2020 | 1/2/2020 | A | PASS |
Tony Young
|
|
|
craig Phone #: ###-####,, interior ok now
|
BLD-Wall Bracing | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PART |
Tell Riley
|
|
|
craig Phone #: ###-####//area near stairs first floor needs blocked and screwed at 4 in oc//all other areas ok//
|
BLD-Framing/Rough-in | 12/24/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Tony Young
|
|
|
Craig Phone #: ###-####
|
BLD-Framing/Rough-in | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PEND |
Tony Young
|
|
|
Craig Phone #: ###-####// ok pending brace
|
BLD-Energy code compliance | 12/20/2019 | 12/23/2019 | 12/23/2019 | P | PASS |
Tony Young
|
|
|
Craig Phone #: ###-####,, will need interior shear inspection,, ok to cover after adding truss brace where cut out
|
BLD-Framing/Rough-in | 12/20/2019 | 12/23/2019 | 12/23/2019 | P | PART |
Tony Young
|
|
|
Craig Phone #: ###-####,, needs truss brace added that was cut out at the top of stairs,, will need interior shear inspection also
|
BLD-Framing/Rough-in | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | PART |
Tony Young
|
|
|
Craig Phone #: ###-####// needs plans,, needs truss bracing,, finish chase framing,, see paint// ok to insulate
|
BLD-Wall Bracing | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Tony Young
|
|
|
Jay Phone #: ###-####
|
BLD-Foundation | 7/10/2019 | 7/11/2019 | 7/11/2019 | P | PART |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Footing | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Tony Young
|
|
|
wall // john Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/13/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/13/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/5/2019 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2019 | | DONE |
|
|
|
|
Telephone call | | | 6/5/2019 | | DONE |
|
|
|
called Craig to let know permits are ready and how much is owed
|
Permit Ready to Issue | | | 6/5/2019 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 5/22/2019 | 5/22/2019 | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
06/04 sfd L1 Paper
|
Routing - PLAN CHECK | 5/24/2019 | | 6/4/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 5/24/2019 | | 5/24/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/22/2019 | | 5/24/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 5/22/2019 | | 5/24/2019 | | PASS |
Angela Hardy
|
|
|
|
Route to Impact Fee Review | 5/22/2019 | 5/25/2019 | 5/23/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/22/2019 | | 5/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/22/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/22/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/22/2019 | | DONE |
|
|
|
|
Application received | | 5/22/2019 | | | |
|
|
|
|