BLD-Ceiling Grid Inspection | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PASS |
Dave Hannah
|
|
|
More clips installed and electrical inspected. Phone # 541 231 2716 Inspection requested via web by Maureen Yogerst
|
BLD-Ceiling Grid Inspection | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PEND |
Dave Hannah
|
|
|
Ceiling grid at the Julia Davis Bandshell
My phone number is 541 ###-#### Inspection requested via web by Maureen Yogerst needs to add wall clips and get elec rough in
|
BLD-Footing | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | FAIL |
Jim Storey
|
|
|
Footing / rebar inspection for wheelchair ramp. Phone #: ###-#### Inspection requested via web by Maureen Yogerst ele conduet under ft . can not displace ft and difarenchal settlement. engineer to address or relocate.
|
BLD-Foundation | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | CANC |
Dave Hannah
|
|
|
Inspect rebar for north wheelchair ramp Phone #: ###-#### >> Inspection requested via web by Maureen Yogerst
|
BLD-Concrete | 12/3/2019 | 12/4/2019 | 12/4/2019 | P | PART |
Tony Young
|
|
|
Not sure if you need to inspect the rebar for the J.D. Bandshell basement. It will be ready Wednesday PM. If not, just call or send me a text at the number provided. Phone #: ###-#### Inspection requested via web by Maureen Yogerst// basement floor with thickened edges ok
|
Print Occupancy Form | | | 12/3/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/17/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/17/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/9/2019 | 10/9/2019 | 10/14/2019 | | PASS |
Carl Westfall
|
|
|
plan mod (Gene Harris bandshell) (at permits desk after plan intake review)
|
Routing - PLAN CHECK | 10/10/2019 | | 10/14/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod plan review approved
|
Plan Reviewer's activity | | | 10/14/2019 | | PASS |
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 10/14/2019 | | DONE |
|
|
|
PLAN MOD - do not reissue
|
Routing - PLAN CHECK | 10/9/2019 | | 10/10/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod intake review approved
|
Plan Modification Accepted | | | 10/9/2019 | | DONE |
|
|
|
plan mod submitted by Carrie Durant of Trout Architects. Remove electrical accessibility lift from project. Relocate green room to first level. Sheets to be uploaded: A201 - New Basement Plan; A204 - New First Floor Plan
|
Fees Due Hold | 7/31/2019 | | 8/1/2019 | | DONE |
Tisha Gallop
|
|
|
|
Fees Due Hold | 7/27/2019 | | 7/30/2019 | | DONE |
Tisha Gallop
|
|
|
|
Fees Due Hold | 7/25/2019 | | 7/26/2019 | | DONE |
Tisha Gallop
|
|
|
|
Issue & PRINT to be Invoiced | | | 7/24/2019 | | DONE |
|
|
|
JV in process
|
Permit Ready to Issue | | | 7/23/2019 | | DONE |
|
|
|
all met-NEED-
GC
Revised Certificate of Value
|
Plan assigned to (CJW) | 6/7/2019 | 7/3/2019 | 7/22/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 06/26/19 (L-3 - 15 days) (eplan - 43 sheets) Gen Harris Bandshell (routed to staff)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/12/2019 | | 7/21/2019 | | PASS |
Carl Westfall
|
|
|
Nicolas Pena (KPFF)
|
Route to Impact Fee Review | 7/11/2019 | 7/14/2019 | 7/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/12/2019 | 7/12/2019 | 7/15/2019 | | PASS |
Mark Scharfen
|
|
|
red lines moved.
|
Routing - PLAN CHECK | 7/12/2019 | | 7/15/2019 | | PASS |
Carl Westfall
|
|
|
Drawings approved after Emailed drawings were uploaded.
|
Routing - PLAN CHECK | 7/11/2019 | | 7/12/2019 | | FAIL |
Carl Westfall
|
|
|
two items not resolved and waiting for structural
|
Routing - PUBLIC WORKS | 7/12/2019 | | 7/12/2019 | | PASS |
Angela Hardy
|
|
|
Service sink added
|
Plan resubmittals received | | | 7/11/2019 | | DONE |
|
|
|
|
Routing - FIRE | 6/7/2019 | 6/7/2019 | 6/25/2019 | | PASS |
Mark Scharfen
|
|
|
06/25/2019-Completed fire review. Made notations on plans, uploaded rev_fire 06.26.2019.pdf. Passed review.
|
Plan resubmittals requested | | | 6/25/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/7/2019 | | 6/25/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 6/25/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/7/2019 | | 6/21/2019 | | FAIL |
Carl Westfall
|
|
|
Nicolas Pena (KPFF)
|
Routing - PLANNING | 6/7/2019 | | 6/11/2019 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 6/7/2019 | | 6/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 6/7/2019 | | 6/11/2019 | | PASS |
Michael Zawacki
|
|
|
No ESC plan required. According to drawings wattles will be installed and good house keeping followed.
|
Routing PW Flood Plain | 6/7/2019 | | 6/10/2019 | | PASS |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - Design Review | 6/7/2019 | | 6/10/2019 | | PASS |
Josh Wilson
|
|
|
No DR required, property not in Design Review overlay
|
Routing - PUBLIC WORKS | 6/7/2019 | | 6/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 6/6/2019 | | PASS |
|
|
|
|
Intake Approval | | | 5/31/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• On the uploaded form 310 check and show the items that need special inspection to coincide with the structural plan sheet S0.1 special inspections table.
|
Application received | | | 5/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2019 12:05PM
|