Permit Information
Permit NumberBLD19-01894
StatusFinaled
Name PETER HITT
Site Address 800 S LA CASSIA DR
Project NameHighland Esthetics - Occupancy
Customer Number 
ePlanReviewNo
Description
(HIGHLAND ESTHETICS – OCCUPANCY) This building does not have a fire sprinkler system. Application for inspection to determine the requirements for the issuance of a Certificate of Occupancy for a new skincare treatment tenant (facials, waxing, etc.) within an existing 1,320 square foot tenant space located within an existing 2,728 square foot building. Egress is directly to the outside at grade. No new work is authorized under this permit except for minor work that may be needed to correct noncompliant conditions that may exist. Painting, carpeting, counter tops, and similar finish work are not required to have a building permit. Compliance is required with the items listed in the plan review report under Referenced Code Sections because noncompliance with these items is believed to constitute a distinct hazard to life and safety or to discriminate against the disabled. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/30/20195/31/20195/31/2019PPASS
DetailsJim Storey
Peter- please call for access Phone #: ###-####
FIRE-Final Inspection5/30/20195/31/20195/31/2019APASS
DetailsTroy Cobbley
Life safety passed

Peter- please call for access Phone #: ###-####
Permanent Occupancy  5/31/2019 DONE
Plan assigned to (CJW)5/24/20195/24/20195/30/2019 PASS
DetailsCarl Westfall
Occupancy - Highland Esthetics (done by 5-30-19)
Routing - PLAN CHECK5/24/2019 5/30/2019 PASS
DetailsCarl Westfall
1st review completed  5/30/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/30/2019 DONE
Telephone call  5/30/2019 DONE
called Peter to let know permit is ready
Permit Ready to Issue  5/30/2019 DONE
Print Occupancy Form  5/30/2019 DONE
Issue PAID IN FULL permit  5/30/2019 DONE
Plans ACCEPTED BY PLAN TECH  5/24/2019 DONE
Recd Pcfee & Taken To Pln CK  5/24/2019 DONE
Intake Approval  5/24/2019 PASS
DetailsCarl Westfall
First Notice 6/10/2019   
Application received 5/24/2019