BLD-Final | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Tell Riley
|
|
|
Stan Phone #: ###-####
|
DOC - Permit Finaled | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PART |
Tell Riley
|
|
|
Stan Phone #: ###-####//final complete--need to change smoke detector in hall to a combo and call for re-inspection//
|
Telephone call | | | 9/16/2019 | | DONE |
|
|
|
Left voicemail for Brad to inform him the manual j is ready to be picked up and per Troy J no plan mod fee for Minor Manual J modification
|
Routing - MECHANICAL | 8/29/2019 | | 9/16/2019 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 9/12/2019 | | DONE |
|
|
|
Manual J. took to troy
|
BLD-Energy code compliance | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Tell Riley
|
|
|
Stan Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Tell Riley
|
|
|
Stan Phone #: 208-841-922//corections made//
|
BLD-Framing/Rough-in | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | PART |
Tell Riley
|
|
|
Stan Phone #: ###-####//ok to insulate only//add truss bracing per plans//need safety glass in windows per plans//
|
Plan Modification Accepted | | | 8/29/2019 | | DONE |
|
|
|
New Manual J submitted and taken to MEC reviewer
|
BLD-Framing/Rough-in | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | NR |
Tell Riley
|
|
|
Stan Phone #: ###-####//talked with Stan--mechanical inspection will need to be passed before he can insulate//
|
BLD-Framing/Rough-in | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | FAIL |
Tell Riley
|
|
|
Stan Phone #: ###-####//correction notice issued//need mechanical inspections,plans and truss documents onsite//
|
BLD-Wall Bracing | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Tell Riley
|
|
|
Bracing corrections made//
|
BLD-Framing/Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | CANC |
Tell Riley
|
|
|
Stan Phone #: ###-####
|
BLD-Wall Bracing | 8/12/2019 | 8/12/2019 | 8/12/2019 | A | FAIL |
Tell Riley
|
|
|
Correction notice issued//need hold downs per plans//panel nailing needs to be fastened to sill plate//
|
BLD-Framing/Rough-in | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | CANC |
Tell Riley
|
|
|
Stan Phone #: ###-####//needs wall bracing inspection//
|
BLD-Foundation | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PART |
Tell Riley
|
|
|
Stanley Phone #: ###-####//wall ok//need to install hold downs//
|
BLD-Footing | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | PASS |
Tell Riley
|
|
|
Stan - concrete coming at 1 Phone #: ###-####//ok per plans//
|
BLD-Foundation | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | CANC |
Tell Riley
|
|
|
Stan-would like as late as possible Phone #: ###-####-inspection not ready
|
OVERRIDE | | | 5/28/2019 | | |
|
|
|
|
Routing Walk-In (Zoning) | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Ethan Mansfield
|
|
|
CUP19-00022
|
Routing Walk-In (BLD) | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/28/2019 | | 5/28/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/28/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/28/2019 | | DONE |
|
|
|
|
Application received | | 5/28/2019 | | | |
|
|
|
|