Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-01918
StatusFinaled
Name ALPINE CONSTRUCTION INC
Site Address 225 N 9TH ST Unit: STE 410
Project NameArmanino - 4th floor T.I.
Customer Number 
ePlanReviewYes
Description
(ARMANINO - SEDGWICK CENTER - SUITE #410) This building is fire sprinkled because it is a high rise. Permit to remodel 5,590 sqft of office space on the 4th floor. Work to include: demo of select non-bearing interior walls, construction of non-load bearing interior walls to create new offices, wellness room, huddle rooms, copy room, storage, open office, break room, conference room, and reception area. Interior finishes shall be in compliance with 2015 IBC chapter 8. Approval is contingent on adhering to the approved plans. Existing high-rise systems shall be maintained. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire Department. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 11/30/201912/4/2019 DONE
This permit finaled on the web by Garrett Bailey
Second Notice 11/4/201911/25/2019 DONE
mailed 12-2-19
First Notice 10/6/201910/25/2019 DONE
mailed 11-1-19
BLD-Final9/25/20199/26/20199/26/2019PPASS
DetailsTony Young
Call hour hour before // garrett Phone #: ###-####
FIRE-Final Inspection9/25/20199/26/20199/26/2019APASS
DetailsJim Page
Fire sprinklker inspection is complete, fire alarm inspection is complete, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection in area of work complete, signatures provided on sign off card for associated trades.

Call hour hour before // garrett Phone #: ###-####
Permanent Occupancy  9/26/2019 DONE
BLD-Ceiling Grid Inspection8/20/20198/20/20198/20/2019PPASS
DetailsDave Hannah
Garrett Phone #: ###-####
BLD-Framing/Rough-in7/8/20197/9/20197/9/2019APASS
DetailsDave Hannah
Garrett Phone #: ###-####
Issue PAID IN FULL permit  6/25/2019 DONE
Print Occupancy Form  6/25/2019 DONE
Routing - PLAN CHECK6/24/2019 6/24/2019 PASS
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  6/24/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  6/24/2019 DONE
met
Need GC
Need rev cert of val
Plan assigned to (M_H)6/5/2019 6/24/2019 DONE
DetailsMichael Hanson
1st review completed - 06/21 #518 L2 ePlan - Armanino TI
Route to Impact Fee Review6/19/20196/22/20196/20/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - PLAN CHECK6/5/2019 6/19/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
1st review completed  6/19/2019 FAIL
DetailsMichael Hanson
Routing - MECHANICAL6/5/2019 6/7/2019 PASS
DetailsChad Schwendiman
Routing - PLUMBING6/5/2019 6/6/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing6/5/2019 6/5/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS6/5/2019 6/5/2019 PASS
DetailsAngela Hardy
Intake Approval  6/4/2019 PASS
DetailsJoe Bruce
Prescreen approved by JHB.
Intake Approval  5/31/2019 FAIL
DetailsJoe Bruce
Provide the following items to complete the prescreen process:
1) The Lighting Compliance COMcheck utilizes an incorrect version of the IECC – see sheet E001. Please have the compliance forms revised to utilize the 2015 IECC version of the energy code.
2) The incorrect building codes are listed on sheet G001. The plumbing code, mechanical code, and electric code all list incorrect versions of the codes that are adopted by the City of Boise Building Department. Please find our current codes at this link: https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/general-building-information-300/301-current-codes/ - Revise the drawings to reflect the currently adopted codes.
Application received  5/28/2019 DONE
Application submitted via PDS Online on May 28 2019 10:49AM