BLD-Final | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Phase I complete- stairs, handrail/guard rail and head height at landing to be addressed at phase II...
|
DOC - Permit Finaled | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 10/7/2019 | 10/9/2019 | 10/9/2019 | P | FAIL |
Brandon Shaw
|
|
|
Need Plm final...
|
BLD-Energy code compliance | 7/3/2019 | 7/5/2019 | 7/5/2019 | A | PASS |
Brandon Shaw
|
|
|
Please call prior to inspection to arrange access. Phone #: ###-#### Inspection requested via web by Dustin Collins
|
BLD-Framing/Rough-in | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PASS |
Brandon Shaw
|
|
|
Please give us a 15 minute warning so we can be present for the inspection. Once this inspection is complete we will finish the air seal and insulation to prepare for the energy inspection. Phone #: ###-#### Inspection requested via web by Dustin Collins
|
Routing - MECHANICAL | 7/1/2019 | | 7/1/2019 | | PASS |
Chad Schwendiman
|
|
|
Revised manaul J
|
Routing - MECHANICAL | 6/13/2019 | | 6/13/2019 | | PASS |
Troy James
|
|
|
Manual j report submitted.
|
Routing Walk-In (BLD) | 5/28/2019 | 5/28/2019 | 5/28/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/28/2019 | | 5/28/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/28/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/28/2019 | | DONE |
|
|
|
|
Application received | | 5/28/2019 | | | |
|
|
|
|