BLD-Final | 3/11/2020 | 3/13/2020 | 3/13/2020 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Energy code compliance | 12/5/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2019 | 12/3/2019 | 12/4/2019 | P | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Conference | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Wall Bracing | 10/1/2019 | 10/4/2019 | 10/4/2019 | P | PART |
Jim Storey
|
|
|
shear // david Phone #: ###-#### exterior ok to cover/ hd at back pannel needs installed.
|
BLD-Conference | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | DONE |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Conference | 8/21/2019 | 8/21/2019 | 8/21/2019 | A | DONE |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Hunter
|
BLD-Footing | 7/24/2019 | 7/24/2019 | 7/24/2019 | P | PASS |
Jim Storey
|
|
|
Darren Phone #: ###-####
|
Telephone call | | | 7/10/2019 | | DONE |
|
|
|
called Bob to verify that all emails for all 17 permits were recieved and informed him that we need all permits signed and returned to be able to release plans.
|
Issue PAID IN FULL permit | | | 7/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2019 | | DONE |
|
|
|
|
Telephone call | | | 7/9/2019 | | DONE |
|
|
|
Emailed permtis BLD19-01957, 01956 & 01928 to bobh@visserbuilding.com
|
OVERRIDE | | | 7/1/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 7/1/2019 | | DONE |
|
|
|
NEED RP
|
Plan assigned to (J_N) | 6/3/2019 | 6/3/2019 | 6/28/2019 | | DONE |
Jenny Nelson
|
|
|
06/20 L2 Townhomes ePlan. 2nd reveiw, failed mech. 1st complete 6/17, waiting for planning, lot lines, code year
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 6/27/2019 | | 6/27/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 6/26/2019 | | 6/26/2019 | | PASS |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 6/25/2019 | | 6/25/2019 | | FAIL |
Troy James
|
|
|
Mechanical engineer stamp must be signed.
|
1st review completed | | | 6/20/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 6/3/2019 | | 6/20/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 6/3/2019 | | 6/17/2019 | | FAIL |
Jenny Nelson
|
|
|
Footing size for three story building, code year
|
Routing - Design Review | 6/13/2019 | | 6/14/2019 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 6/3/2019 | 6/6/2019 | 6/4/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/3/2019 | | 6/4/2019 | | FAIL |
Troy James
|
|
|
See eplan
|
Routing - Addressing | 6/3/2019 | | 6/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/3/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/3/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/3/2019 | | PASS |
|
|
|
|
Intake Approval | | | 5/31/2019 | | FAIL |
|
|
|
5-31-19 Please provide Manual J for each unit. Please leave bottom right corner open for City Approved Stamps (E1-00_Site Electrical Plan for example)
|
Intake Approval | | | 5/30/2019 | | FAIL |
|
|
|
Per the conversation through email, please fill out new applications for each address with the correct information for each townhome and re upload them to the documents folder. Please provide a Site Plan: Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines.
|
Application received | | | 5/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 29 2019 9:36AM
|