BLD-Final | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PASS |
Dave Hannah
|
|
|
Dustin *screened* Phone #: ###-####
|
DOC - Permit Finaled | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/26/2020 | 5/27/2020 | 5/27/2020 | A | FAIL |
Mike Jordan
|
|
|
Screened- Dustin Phone #: ###-####. Provide smoke detector/carbon monoxide detectors in basement and outside of bedroom upstairs. All detectors shall be interconnected. Handrails shall return to wall, and measure 34 to 38 inches. Provide guard rail around open side of stairs. Correction notice posted.
|
BLD-Final | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | FAIL |
Dave Hannah
|
|
|
Screened- Dustin Phone #: ###-#### needs smoke and co2 detectors up and down stars hand rails for stairs into basement cover paper or remove on insulation in furnace rm
|
BLD-Energy code compliance | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
Brandon Shaw
|
|
|
access to electronic door lock 8181 Phone #: ###-#### Inspection requested via web by Dustin West
|
BLD-Framing/Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PART |
Dave Hannah
|
|
|
call ahead - dustin Phone #: ###-#### ok to insulate basement but needs to check fire blocking at top plate at energy
|
BLD-Conference | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | DONE |
Dave Hannah
|
|
|
dUSTIN Phone #: ###-####
|
BLD-Concrete | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PASS |
Dave Hannah
|
|
|
rebar basement walls- Dustin Phone #: ###-####
|
BLD-Foundation | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | NR |
Dave Hannah
|
|
|
Dustin Phone #: ###-####
|
BLD-Footing | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | NR |
Dave Hannah
|
|
|
Dustin Phone #: ###-####
|
BLD-Footing | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Dave Hannah
|
|
|
Dustin Phone #: ###-####
|
BLD-Foundation | 10/31/2019 | 11/1/2019 | 11/4/2019 | A | PART |
Dave Hannah
|
|
|
please call 30 min ahead // basement wall // Dustin Phone #: ###-#### ok to place first sections of walls
|
BLD-Footing | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PART |
Tony Young
|
|
|
call to meet there // Dustin Phone #: ###-####.. portions of basement footings are work in progress,,
|
OVERRIDE | | | 7/31/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 5/29/2019 | 5/29/2019 | 7/31/2019 | | PASS |
Josh Bogle
|
|
|
06/04 foundation, paper - 1st done
|
Routing - PLAN CHECK | 7/31/2019 | | 7/31/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 7/31/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/31/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 7/31/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/31/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/3/2019 | | 6/3/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 6/3/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (Zoning) | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 5/29/2019 | 5/29/2019 | 5/29/2019 | P | PASS |
Josh Bogle
|
|
|
took in for level two review (waiting on engineering calc pages)
|
Application received | | 5/29/2019 | | | |
|
|
|
|
Application received | | 5/29/2019 | | | |
|
|
|
|