Permit Information
Permit NumberBLD19-01958
StatusFinaled
Name VISSER BUILDING CO
Site Address 2254 W KOOTENAI ST
Project NameKootenai Townhomes - Bldg B
Customer NumberEPLAN BLD19-01929,BLD19-01958-01959
ePlanReview 
Description
**PRESCRIPTIVE ENERGY REQUIREMENTS** **SPECIAL INSPECTIONS** (THREE PERMITS FILED UNDER BLD19-01929) (THREE PERMITS FILED UNDER BLD19-01929)Permit for the construction of a new 1617 sq. ft., three story (first story 303 sq. ft., second story 657 sq. ft., third story 657 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately 353 sq. ft. of covered patio/porch and a 280 sq. ft. attached garage per the approved plans and any notations. R-3D zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/28/20203/2/20203/2/2020PPASS
DetailsJim Storey
David Phone #: ###-####
DOC - Permit Finaled3/2/20203/2/20203/2/2020PPASS
DetailsJim Storey
BLD-Blower Door Test Results3/2/20203/2/20203/2/2020PDONE
DetailsJim Storey
David Phone #: ###-#### 5.3
BLD-Final2/24/20202/24/20202/24/2020PFAIL
DetailsJim Storey
David Phone #: ###-####
BLD-Energy code compliance11/27/201911/29/201911/29/2019APASS
DetailsJim Storey
David Phone #: ###-####
BLD-Framing/Rough-in11/21/201911/22/201911/22/2019PPASS
DetailsJim Storey
David Phone #: ###-####
BLD-Conference10/25/201910/28/201910/28/2019APASS
DetailsJim Storey
David Phone #: ###-####
BLD-Conference10/10/201910/11/201910/16/2019PPASS
DetailsJim Storey
David Phone #: ###-####
BLD-Conference10/2/201910/2/201910/2/2019PPEND
DetailsJim Storey
david Phone #: ###-#### david Phone #: ###-#### aproved plan missing p/l protection at above roof at top of stair enclosers and roof protection. pending arch responce.
BLD-Conference10/1/201910/2/201910/2/2019ADEFR
DetailsJim Storey
david \ Phone #: ###-####
BLD-Wall Bracing9/25/20199/27/20199/27/2019PPASS
DetailsBrandon Shaw
shear // David Phone #: ###-####
BLD-Footing7/25/20197/26/20197/26/2019APASS
DetailsJim Storey
Daren Phone #: ###-####
Telephone call  7/10/2019 DONE
called Bob to verify that all emails for all 17 permits were recieved and informed him that we need all permits signed and returned to be able to release plans.
Issue PAID IN FULL permit  7/8/2019 DONE
Inspection Record Card- Bld  7/8/2019 DONE
Telephone call  7/8/2019 DONE
email to bobh@hvisserbuilding.com all three permits bld19-01929, 01959 & 01958
OVERRIDE  6/28/2019  
Permit Ready to Issue  6/28/2019 DONE
DO NOT ISSUE WITHOUT BLD19-01929, BLD19-01958 & BLD19-01959
ALL MET-NEED RP
Plan assigned to (J_N)6/3/20196/3/20196/27/2019 DONE
DetailsJenny Nelson
06/20 L2 Townhomes ePlan. 2nd review, failed mech. 1st complete 6/17, waiting for planning, lot lines. code year
Routing - MECHANICAL6/27/2019 6/27/2019 PASS
DetailsTroy James
PLANS/APPL TAKEN TO FRONT DESK  6/27/2019 DONE
DetailsJenny Nelson
Routing - PLAN CHECK6/26/2019 6/26/2019 PASS
DetailsJenny Nelson
1st review completed  6/20/2019 DONE
DetailsJenny Nelson
Routing - PLANNING6/3/2019 6/20/2019 PASS
DetailsLeon Letson
Routing - PLAN CHECK6/3/2019 6/17/2019 FAIL
DetailsJenny Nelson
Footing size, code year
Routing - Design Review6/13/2019 6/14/2019 PASS
DetailsAndrea Tuning
Route to Impact Fee Review6/3/20196/6/20196/4/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL6/3/2019 6/4/2019 FAIL
DetailsTroy James
Routing - Addressing6/3/2019 6/3/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS6/3/2019 6/3/2019 PASS
DetailsAngela Hardy
Plans ACCEPTED BY PLAN TECH  6/3/2019  
Recd Pcfee & Taken To Pln CK  6/3/2019  
Intake Approval  6/3/2019 PASS
Intake Approval  5/31/2019 FAIL
5-31-19 Please provide a Manual J for each unit. Please leave bottom right corner open on the plan sheets for City Approved Stamps (E0-01_Electrical Specifications for example)
Intake Approval  5/30/2019 FAIL
Per the conversation through email, please fill out new applications for each address with the correct information for each townhome and re upload them to the documents folder. Please provide a Site Plan: Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines.
Application received 5/30/2019