BLD-Final | 4/13/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Jim Storey
|
|
|
Screened // David Phone #: ###-####
|
DOC - Permit Finaled | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 4/17/2020 | 4/17/2020 | 4/17/2020 | A | DONE |
Jim Storey
|
|
|
Screened // David Phone #: ###-#### 4.0
|
BLD-Conference | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Energy code compliance | 2/7/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Mike Jordan
|
|
|
David Phone #: ###-####
|
BLD-Energy code compliance | 2/5/2020 | 2/7/2020 | 2/10/2020 | P | NR |
Dave Hannah
|
|
|
david Phone #: ###-####
|
BLD-Framing/Rough-in | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Wall Bracing | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PASS |
Jim Storey
|
|
|
shear // David Phone #: ###-####
|
Telephone call | | | 7/10/2019 | | DONE |
|
|
|
called Bob to verify that all emails for all 17 permits were recieved and informed him that we need all permits signed and returned to be able to release plans.
|
Issue PAID IN FULL permit | | | 7/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/27/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 6/3/2019 | 6/3/2019 | 6/27/2019 | | DONE |
Jenny Nelson
|
|
|
06/20 L2 Townhomes ePlan. 2nd review, failed mech. 1st complete 6/17, lot lines, code year
|
Routing - MECHANICAL | 6/27/2019 | | 6/27/2019 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/27/2019 | | DONE |
|
|
|
*** DO NOT ISSUE WITHOUT BLD19-01931 AND BLD19-01961
ALL MET
NEED RP
|
Routing - PLAN CHECK | 6/26/2019 | | 6/26/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 6/20/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 6/3/2019 | | 6/20/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 6/3/2019 | | 6/17/2019 | | FAIL |
Jenny Nelson
|
|
|
Footing size, code year
|
Routing - Design Review | 6/13/2019 | | 6/14/2019 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 6/3/2019 | 6/6/2019 | 6/4/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/3/2019 | | 6/3/2019 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 6/3/2019 | | 6/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/3/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/3/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/3/2019 | | PASS |
|
|
|
|
Intake Approval | | | 5/31/2019 | | FAIL |
|
|
|
Please provide a Manual J for each unit. Please leave the bottom right corner open for the City Approved Stamp on all plans (E1-00_Site Electrical Plan for example)
|
Intake Approval | | | 5/30/2019 | | FAIL |
|
|
|
Per the conversation through email, please fill out new applications for each address with the correct information for each townhome and re upload them to the documents folder. Please provide a Site Plan: Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines.
|
Application received | | 5/30/2019 | | | |
|
|
|
|