Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | 9/19/2019 | 9/19/2019 | 10/29/2019 | | DONE |
Mike Jordan
|
|
|
mailed 11-1
|
BLD-Final | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | FAIL |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Provide suite address, Install miorror ADA bathroom.
|
FIRE-Final Inspection | 8/28/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. A suite number is to be provided prior to a building inspection as discussed. Jim Phone #: ###-#### Inspection requested via web by Jim Wellman
|
BLD-Ceiling Grid Inspection | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | FAIL |
Tell Riley
|
|
|
Jim Wellman Phone #: ###-#### Inspection requested via web by Jim Wellman//need fire sprinkler inspection// replace insulation--add insulation where missing in ceiling//
|
BLD-Framing/Rough-in | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior steel stud framed walls and hardlids only ok, pending mech. and plumbing r.i. inspections.
|
(F) Reprint permit | | | 6/26/2019 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2019 | | DONE |
|
|
|
emailed chris.steed@steedconstruction.com to sign permit for me again. I lost the orig and so there is nothing in the docs
|
(F) Reprint permit | | | 6/17/2019 | | DONE |
|
|
|
2nd request to sign
|
Print Occupancy Form | | | 6/17/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 6/10/2019 | | 6/13/2019 | | DONE |
Michael Hanson
|
|
|
06/14 #518 L2 ePLan - Vanilla T.I. Suite #180
|
1st review completed | | | 6/13/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/13/2019 | | DONE |
|
|
|
all met-email fees due to Josh Kincaid -Need GC
Need Rev Val
|
Issue PAID IN FULL permit | | | 6/13/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/3/2019 | | 6/13/2019 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (JG) | 6/3/2019 | 6/3/2019 | 6/10/2019 | | DEFR |
Javier Guzman
|
|
|
06/14 L2 Vanilla T.I. Suite #180 ePlan
|
Routing - FIRE | 6/3/2019 | 6/3/2019 | 6/10/2019 | | PASS |
Mark Scharfen
|
|
|
06.10.2019-Completed fire review. Made notations on plans, no report. Passed review.
|
Routing - MECHANICAL | 6/3/2019 | | 6/6/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Addressing | 6/3/2019 | | 6/5/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/5/2019 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Routing - Erosion and Sediment | 6/3/2019 | | 6/4/2019 | | PASS |
Michael Zawacki
|
|
|
No ESC needed
|
Routing - PLUMBING | 6/3/2019 | | 6/4/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 6/3/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 5/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2019 4:26PM
|