Third Notice | | 12/2/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
Second Notice | | 11/4/2019 | 11/27/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | | 9/16/2019 | 10/25/2019 | | DONE |
|
|
|
mailed 11-1-19
|
FIRE-Final Inspection | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. 2 Heat detectors have been installed in the penthouse per the alternate agreement to allow fire sprinklers to be omitted from penthouse. Final life fire safety inspection for area of work complete, signatures provided for inspected trades on signature card.
Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas
|
BLD-Final | 9/6/2019 | 9/6/2019 | 9/6/2019 | A | PASS |
Dave Hannah
|
|
|
Call prior to going Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas
|
Permanent Occupancy | | | 9/6/2019 | | DONE |
|
|
|
|
BLD-Final | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | CANC |
Dave Hannah
|
|
|
As early as possible Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas Inspection cancelled via mobile web on Thursday, September 05, 2019.
|
BLD-Ceiling Grid Inspection | 8/26/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas
|
BLD-Ceiling Grid Inspection | 8/21/2019 | 8/26/2019 | 8/26/2019 | P | PART |
Dave Hannah
|
|
|
Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas se corner ok to flood
|
BLD-Framing/Rough-in | 7/9/2019 | 7/9/2019 | 7/10/2019 | P | PASS |
Dave Hannah
|
|
|
As early as possible Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas
|
Issue PAID IN FULL permit | | | 7/9/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/9/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 6/6/2019 | 6/6/2019 | 7/8/2019 | | PASS |
Joe Bruce
|
|
|
07/09 (2nd Rev) 07/01 (L3) McMillen Jacobs Shoreline, ePlan
|
Routing - PLAN CHECK | 7/2/2019 | | 7/8/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/8/2019 | | DONE |
|
|
|
all met: corywiltshire@esiconstruction.com
Need GC
Need rev cert of val
|
Elevation Cert Rec'd-Prelim | | | 7/3/2019 | | DONE |
|
|
|
|
Routing PW Flood Plain | 7/3/2019 | | 7/3/2019 | | PASS |
Jason C. Taylor
|
|
|
All electrical equipment must be 1' above the BFE for the structure. Please raise all equipment prior to final occupancy. Jason Taylor 2086087171
|
Route to Impact Fee Review | 7/2/2019 | 7/5/2019 | 7/2/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 7/2/2019 | | DONE |
Joe Bruce
|
|
|
Received email from applicant with plan review responses.
|
Routing - PLANNING | 7/2/2019 | | 7/2/2019 | | PASS |
David Moser
|
|
|
Building complies with floodplain requirements
|
1st review completed | | | 7/1/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 7/1/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 6/6/2019 | 6/6/2019 | 6/28/2019 | | PASS |
Mark Scharfen
|
|
|
06.28.2019-completed fire review. Uploaded rev_fire 06.28.2019.pdf
|
Routing - PLAN CHECK | 6/6/2019 | | 6/28/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - MECHANICAL | 6/6/2019 | | 6/12/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/6/2019 | | 6/11/2019 | | FAIL |
David Moser
|
|
|
The project does not comply with the substantial improvement condition of approval for CFH19-00015
|
Routing PW Flood Plain | 6/6/2019 | | 6/11/2019 | | FAIL |
Jason C. Taylor
|
|
|
Project exceeds the 50% valuation and will need to comply with the substantial improvement section of the Floodplain Ordinance. Please provide an elevation certificate from a Licensed Surveyor using the newer Preliminary FIRM Panles provided by FEMA. Let me know if you have any questions. Jason Taylor ###-####
|
Routing - Addressing | 6/6/2019 | | 6/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/6/2019 | | 6/6/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLUMBING | 6/6/2019 | | 6/6/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 6/3/2019 | | PASS |
|
|
|
|
Application received | | | 5/31/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 31 2019 8:19AM
|