BLD-Final | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Mike Jordan
|
|
|
JIm Phone #: ###-####
|
DOC - Permit Finaled | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 3/2/2020 | 3/2/2020 | 3/2/2020 | A | DONE |
Mike Jordan
|
|
|
4.7
|
BLD-Final | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | FAIL |
Mike Jordan
|
|
|
Carl Phone #: ###-####. Complete fire cauliking in garage and provide blower door test results.
|
BLD-Framing/Rough-in | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Mike Jordan
|
|
|
sheet rock framing // Jim Phone #: ###-####
|
Release Hold on Job | | | 11/6/2019 | | DONE |
|
|
|
Removed parcel hold because they paid the reinspection fee per Michael Z
|
BLD-Framing/Rough-in | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Energy code compliance | 10/25/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Wall cover | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Framing/Rough-in | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk
|
BLD-Framing/Rough-in | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | FAIL |
Mike Jordan
|
|
|
Complete lateral bracing on A3 trusses. Complete fireblocking on furdowns. Nail off all simpson hangars and provide fixes for trusses at entry way. Ok to insulate.
|
BLD-Framing/Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | CANC |
Mike Jordan
|
|
|
JIM Phone #: ###-####. Moved to pm inspection.
|
BLD-Framing/Rough-in | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | FAIL |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Conference | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | DONE |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Wall Bracing | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Wall Bracing | 9/27/2019 | 9/27/2019 | 9/27/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Funk//need to address nailing and blocking at portal frames//sthds in wrong locations//windows added in shear location at front entry//2 hr wall contruction does not match plans//
|
BLD-Wall Bracing | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Carl Phone #: ###-####. Needs to provide a full set of approved plans. Notes say there should be a total of eight pages of construction docs. Omly seven are provided. Wall bracing plans are incomplete, missing schedules. Also noted that 2hr. wall is not continous or constructed per plans.
|
BLD-Foundation | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
stem wall // Willie Phone #: ###-####
|
BLD-Footing | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | PASS |
Mike Jordan
|
|
|
Sergio Phone #: ###-####
|
BLD-Footing | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | FAIL |
Mike Jordan
|
|
|
Sergio Phone #: ###-####. Approved plans shows duplex 1hr. wall seoeration, per scope of work, townhouses are being constructed, which require a 2hr. seperation. Plans to be resubmitted.
|
BLD-Footing | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | FAIL |
Mike Jordan
|
|
|
surgeo Phone #: ###-####. No city approved plans on site.
|
Issue PAID IN FULL permit | | | 7/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/30/2019 | | DONE |
|
|
|
|
Telephone call | | | 7/26/2019 | | DONE |
|
|
|
GC will be here next week to submit 302 and sign for permits
|
OVERRIDE | | | 7/24/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 7/10/2019 | 7/10/2019 | 7/24/2019 | | DONE |
Jenny Nelson
|
|
|
2nd review, waiting for planning. 1st complete 7/12, wall bracing, floor joist main floor, ul or ga
|
Routing - PLANNING | 7/22/2019 | | 7/24/2019 | | PASS |
Brent Moore
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/24/2019 | | DONE |
|
|
|
ALL MET -NEED RP
DO NOT ISSUE WITHOUT BLD19-02010
7-26-19 owner changed GC- needs to provide New GC
|
Routing - PLAN CHECK | 7/22/2019 | | 7/22/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 7/12/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 7/10/2019 | | 7/12/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 7/10/2019 | 7/13/2019 | 7/11/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/10/2019 | | 7/10/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/10/2019 | | 7/10/2019 | | FAIL |
Brent Moore
|
|
|
Need to show distance from 2nd floor to west property line. 15' setback required.
|
Routing - Addressing | 7/10/2019 | | 7/10/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2019 | | 7/10/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/10/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/10/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/10/2019 | | DONE |
|
|
|
|
Meeting | | | 7/9/2019 | | DONE |
|
|
|
emailed brandon that 02010 needs to be paid too
|
Intake Approval | | | 6/27/2019 | | FAIL |
|
|
|
1. Stair section detail showing dimensions of treads, risers, headroom, handrails, & guard requirements.
2. elevation height to top of roof
3. energy compliance- REScheck
4. Label furnace and air conditioner
5. Light switches of top and bottom of stairs for both townhomes.
|
Intake Approval | | | 6/7/2019 | | FAIL |
|
|
|
as per our conversation-please upload all apps for the separate townhouses, manual J's and revised site plan with correct info on it. Please make sure to name the drawings correctly and make sure you leave the bottom right corner open for our approved stamp. Once we get all the drawings and other info we will do the prescreen accordingly
|
Application received | | | 6/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 3 2019 8:12AM
|