BLD-Final | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by rick pew
|
BLD-Final | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | NR |
Mike Jordan
|
|
|
Mark ###-#### Inspection requested via web by rick pew. Needs to final electrical first.
|
BLD-Final | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PART |
Dave Hannah
|
|
|
Will Phone #: ###-#### ok to open coffee bar
|
BLD-Other | 9/23/2019 | 9/23/2019 | 9/23/2019 | A | NR |
Dave Hannah
|
|
|
Coffee Bar Area Inspection. Phone #: ###-#### Inspection requested via web by Will Longstroth
|
FIRE-Final Inspection | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler modifications are complete, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safey inspection for area of work complete.
Will Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/21/2019 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | 6/6/2019 | | 6/20/2019 | | PASS |
Michael Hanson
|
|
|
Stamped, signed, and dated cover sheet G0.1.
|
1st review completed | | | 6/20/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/20/2019 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Plan assigned to (M_H) | 6/6/2019 | | 6/20/2019 | | DONE |
Michael Hanson
|
|
|
06/24 #518 L2 ePlan - Whole Foods
|
Routing - PLAN CHECK | 6/6/2019 | | 6/20/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing PW Environmental | 6/7/2019 | | 6/19/2019 | | PASS |
Terry Alber
|
|
|
JR Smith grease interceptor in coffee bar acceptable.
|
Routing - FIRE | 6/6/2019 | 6/6/2019 | 6/17/2019 | | PASS |
Mark Scharfen
|
|
|
06.17.2019-Completed fire review. Made notations on plans. No report needed.
|
Routing - MECHANICAL | 6/6/2019 | | 6/12/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 6/6/2019 | | 6/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLUMBING | 6/6/2019 | | 6/6/2019 | | PASS |
Daryl Spivey
|
|
|
Installed equipment may require additional backflow protection.
|
Intake Approval | | | 6/5/2019 | | PASS |
Michael Hanson
|
|
|
|
Application received | | | 6/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 3 2019 3:40PM
|