BLD-Final | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Jim Storey
|
|
|
Call half hour before // Mike Phone #: ###-####
|
DOC - Permit Finaled | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/30/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, final life fire safety inspection for area of work complete, card has been signed.
|
BLD-Foundation | 8/12/2019 | 8/13/2019 | 8/13/2019 | P | PART |
Tony Young
|
|
|
concrete at 3 // Mike Phone #: ###-####// 8 piers ,, work in progress,, pending special inspection report
|
Issue PAID IN FULL permit | | | 8/9/2019 | | DONE |
|
|
|
emailed kevin.raymes@steedconstruction.com to sign the building and ESC permits and send back. Email came back with an out of the office reply so sent another one to chris.steed@steedconstruction.com in case they need it before the 12th
|
Inspection Record Card- Bld | | | 8/9/2019 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2019 | | DONE |
|
|
|
Victor emailed wanting to know what was needed-I told him the GC needed to get us the RP, 302 & 306 forms
|
OVERRIDE | | | 7/25/2019 | | |
|
|
|
|
Plan assigned to (JG) | 6/13/2019 | 6/13/2019 | 7/25/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev comp, 06/25 L2 - Gravity Payments ePlan
|
Routing - PLAN CHECK | 7/17/2019 | | 7/25/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/25/2019 | | DONE |
|
|
|
MET NATE.WALRATH@STEEDCONSTRUCTION.COM
Need GC
Need rev cert of val
Need RP-met
|
Routing Off Site - STRUCTURAL | 7/17/2019 | | 7/24/2019 | | PASS |
Javier Guzman
|
|
|
signed off in eplan by KPFF Sidney Gold
|
Route to Impact Fee Review | 6/25/2019 | 6/28/2019 | 6/27/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/13/2019 | | 6/25/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 6/13/2019 | | 6/25/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in eplan by KPFF Sidney Gold
|
1st review completed | | | 6/25/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 6/13/2019 | 6/13/2019 | 6/21/2019 | | PASS |
Mark Scharfen
|
|
|
06.21.2019-Completed fire review. No report needed. Approved.
|
Routing PW Drainage | 6/14/2019 | | 6/14/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 6/13/2019 | | 6/14/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 6/13/2019 | | 6/14/2019 | | PASS |
Michael Zawacki
|
|
|
Waiver approved
|
Routing - Design Review | 6/13/2019 | | 6/14/2019 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 6/12/2019 | | PASS |
Joe Bruce
|
|
|
Prescreen approved by JHB.
|
Intake Approval | | | 6/5/2019 | | FAIL |
Joe Bruce
|
|
|
Provide the following items to complete the prescreen process:
1) Provide form #310 - “Statement of Special Inspections” completed by the design engineer for the items noted in the structural notes which require a special inspector to perform inspection per chapter 17 of the 2015 IBC. Sheet S001 notes (7) seven different special inspections required for this project.
|
Application received | | | 6/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2019 6:56AM
|