Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD19-02030
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 2421 S TRAPPER PL
Project NameHarris North Lot 4 Block 1
Customer Number 
ePlanReviewYes
Description
***W.U.I. FOOTHILLS LOT ZONE A; CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR MATERIALS REQUIRED*** Permit for the construction of a new 3590 sq. ft., two story (first story 1887 sq. ft., second story 1703 sq. ft.) single family dwelling with 5 bedrooms, 3.5 bathrooms, approximately 431 sq. ft. of covered patio/porch and a 993 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. SP-01 zoning and setbacks per planning. *** RDP*** ***SPRINKLERS ARE NOT REQUIRED***LGMA letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/27/201912/30/201912/30/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled12/30/201912/30/201912/30/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results12/30/201912/30/201912/30/2019ADONE
DetailsBrandon Shaw
ACH50- 3.92
PubWorks Occupancy Approval12/27/201912/27/201912/27/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Other10/2/201910/2/201910/2/2019PPASS
DetailsBrandon Shaw
Les-fire soffit Phone #: ###-####
BLD-Energy code compliance9/26/20199/26/20199/26/2019PPASS
DetailsBrandon Shaw
les Phone #: ###-####
BLD-Framing/Rough-in9/23/20199/23/20199/23/2019PPASS
DetailsBrandon Shaw
Les Phone #: ###-####
BLD-Framing/Rough-in9/5/20199/6/20199/6/2019ACANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Gus Brandon
BLD-Wall Bracing8/20/20198/21/20198/20/2019APART
DetailsBrandon Shaw
First floor only...
BLD-Foundation7/23/20197/23/20197/23/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing7/22/20197/22/20197/22/2019PPASS
DetailsBrandon Shaw
Work in progress...
PubWorks Subgrade Approval7/22/20197/22/20197/22/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
OVERRIDE  7/19/2019  
Plan assigned to (RDP)6/10/20196/10/20197/19/2019 DONE
DetailsRob Patrick
06/27 sfd L2 ePlan...06/27 Failed
Issue PAID IN FULL permit  7/19/2019 DONE
Inspection Record Card- Bld  7/19/2019 DONE
Routing - PLAN CHECK7/19/2019 7/19/2019 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  7/19/2019 DONE
DetailsRob Patrick
Permit Ready to Issue  7/19/2019 DONE
Routing PW Grading-Hillside7/18/2019 7/18/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

1st review completed  6/27/2019 FAIL
DetailsRob Patrick
Routing - PLAN CHECK6/10/2019 6/27/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Routing PW Grading-Hillside6/10/2019 6/18/2019 FAIL
DetailsMelissa Jannusch
See changemarks in ePlan
Route to Impact Fee Review6/10/20196/13/20196/11/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - FIRE6/10/20196/10/20196/11/2019 PASS
DetailsLee G Meredith
06/24-2421 S Trapper Pl Residential ePlan 404

Sprinklers are not required.
Routing - MECHANICAL6/10/2019 6/11/2019 PASS
DetailsTroy James
Routing - Addressing6/10/2019 6/11/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS6/10/2019 6/10/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment6/10/2019 6/10/2019 PASS
DetailsMichael Zawacki
Harris North, foothills lot.
Intake Approval  6/10/2019 PASS
Recd Pcfee & Taken To Pln CK  6/10/2019 DONE
Routing - PLANNING6/10/2019 6/10/2019 PASS
DetailsJeff Lowe
Application received  6/4/2019 DONE
Application submitted via PDS Online on Jun 4 2019 10:26AM