BLD-Aging Inspection | 6/19/2020 | 6/19/2020 | 6/23/2020 | | CANC |
Tell Riley
|
|
|
|
BLD-Final | 2/6/2020 | 2/6/2020 | 2/6/2020 | P | PASS |
Tell Riley
|
|
|
final review of special inspection report reviewed onsite provided by MTI for footings, foundations, and post installed anchors in concrete////original inspections completed under BLD19-00843--refer to this permit for inspections//
|
BLD-Foundation | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//original inspections completed under BLD19-00843--refer to this permit for inspections//
|
BLD-Conference | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter
|
FIRE-Final Inspection | 2/4/2020 | 2/5/2020 | 2/5/2020 | A | CANC |
Troy Cobbley
|
|
|
No life safety sign off required for this permit.
Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Final | 2/3/2020 | 2/5/2020 | 2/5/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Zach Carter Inspection cancelled from web by: Zach Carter
|
BLD-Conference | 1/14/2020 | 1/21/2020 | 1/21/2020 | P | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Framing/Rough-in | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//new GB over existing framing//insulation ok, vapor barrier installed//no electrical or plumbing//
|
BLD-Conference | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter
|
Issue PAID IN FULL permit | | | 6/14/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/5/2019 | 6/8/2019 | 6/6/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
all met-Need
GC -met
RP-met
emailed GC see Telephone activity
Met- Revised Certificate of Value
|
Telephone call | | | 6/6/2019 | | DONE |
|
|
|
Emailed- mmcanulty@neudesignarch.com to informed them what the fees are and that we still need the GC and RP
|
Plan assigned to (JAR) | 6/5/2019 | 6/5/2019 | 6/5/2019 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 6/5/2019 | | 6/5/2019 | | PASS |
Julie Romig
|
|
|
FOUNDATION PERMIT ONLY. NO VERTICAL CONSTRUCTION.
Work is allowed to be done at the owners risk; any items found to be not in compliance upon approval of the plans shall be corrected prior to any further work being completed.
Refer to BLD19-00843 for all department reviews.
|
1st review completed | | | 6/5/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/5/2019 | | PASS |
Julie Romig
|
|
|
Prescreen approved 6-4-19 / fees paid 6-5-19
|
Application received | | | 6/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2019 12:31PM
|