BLD-Conference | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Charles Smith exterior ok to cover wip
|
BLD-Conference | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Jim Storey
|
|
|
Please call approx. 10 minutes before arriving at site so I can meet you there. Phone #: ###-#### Inspection requested via web by Charles Smith framing ok/ exterior ok to cover. pending ele ri.
|
BLD-Foundation | 9/15/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Jim Storey
|
|
|
Please call approx 10 min before inspection. Phone #: ###-#### Inspection requested via web by Charles Smith//rebar/insulation ok
|
BLD-Foundation | 7/15/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Jim Storey
|
|
|
Jerry- foundation wall inspection Phone #: ###-####
|
BLD-Footing | 7/12/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Jim Storey
|
|
|
Jerry Phone #: ###-####
|
Route to Impact Fee Review | 7/12/2019 | 7/17/2019 | 7/12/2019 | | PASS |
Eric Bilimoria
|
|
|
|
Plan assigned to (J_N) | 6/12/2019 | 6/12/2019 | 7/12/2019 | | DONE |
Jenny Nelson
|
|
|
2nd review, still need man j for mech. 1st complete 6/12, failed
|
Routing - PLAN CHECK | 7/12/2019 | | 7/12/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 7/12/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/12/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 7/10/2019 | | 7/10/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Plan resubmittals received | | | 7/9/2019 | | DONE |
|
|
|
Manual S's and structural plan
|
Routing - PLAN CHECK | 6/26/2019 | | 6/26/2019 | | PASS |
Jenny Nelson
|
|
|
|
Plan assigned to (JAB) Josh | 6/5/2019 | 6/5/2019 | 6/12/2019 | | DEFR |
Josh Bogle
|
|
|
6/11 ADU, paper
|
Routing - PLAN CHECK | 6/5/2019 | | 6/12/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 6/12/2019 | | 6/12/2019 | | FAIL |
Chad Schwendiman
|
|
|
Emailed corrections to applicant.
|
1st review completed | | | 6/12/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 6/5/2019 | | 6/10/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - PUBLIC WORKS | 6/10/2019 | | 6/10/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 6/10/2019 | | 6/10/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 6/7/2019 | | 6/7/2019 | | PASS |
Doug Chausow
|
|
|
ADU Address 1729 S Helel St
|
Plans ACCEPTED BY PLAN TECH | | | 6/5/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/5/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/5/2019 | | DONE |
|
|
|
|
Application received | | 6/5/2019 | | | |
|
|
|
|