Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD19-02117
StatusFinaled
Name PACIFIC NORTH CONTRACTORS INC
Site Address 201 W BOISE AVE
Project NameJacksons #173 Remodel
Customer Number 
ePlanReviewYes
Description
(JACKSONS)***PLAN MOD TO ADD RTU'S*** ***Special inspections are required see 310 form*** This building is not fire sprinkled. Permit to remodel the exterior of an existing 11,477 sqft. mercantile building. Work to include Demo work: Select exterior wall elements, awnings, and finishes. New work: re-roof, awnings, structural, and electrical work. Approval is contingent on adhering to the approved plans. Structural engineering provided. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/19/20208/11/2020 DONE
MAILED 8-14-2020
First Notice5/29/20205/29/20207/9/2020 DONE
DetailsBrandon Shaw
mailed 7-9-2020
BLD-Aging Inspection5/29/20205/29/20205/29/2020 DEFR
DetailsBrandon Shaw
DOC - Permit Finaled5/29/20205/29/20205/29/2020PPASS
DetailsBrandon Shaw
BLD-Final1/16/20201/16/20201/16/2020PNR
DetailsJim Storey
open ele permit
BLD-Final1/15/20201/16/20201/16/2020ANR
DetailsJim Storey
Nate Phone #: ###-#### open ele permit
FIRE-Final Inspection1/16/20201/16/20201/16/2020APASS
DetailsJim Page
Fire alarm inspection complete, no fire sprinklers, fire extinguishers not required for this scope, final life fire safety inspection for scope of work complete, signature card not available at time of inspection, no signatures provided.
Zoning Approval1/6/20201/6/20201/6/2020 PASS
DetailsKatelyn Menuge
PubWorks Occupancy Approval12/11/201912/11/201912/11/2019 DONE
DetailsTiffany Lowery
BLD-Final12/9/201912/9/201912/9/2019PPART
DetailsBrandon Shaw
Temp C of O is approved for store only...
All permits to be finaled when canopy and fuel island are fininshed...
FIRE-Final Inspection12/9/201912/9/201912/9/2019PPART
DetailsTroy Cobbley
A temp for life safety is ok'd by Joe Bruce until the gas islands have been completed/inspected. Previous corrections have been addressed. Nate Phone #: ###-####
Print Occupancy Form  12/5/2019 DONE
Zoning Approval Temp12/4/201912/4/201912/4/2019 PASS
DetailsKatelyn Menuge
Bond for Landscape
Inspection Record Card- Bld  12/2/2019 DONE
Plan assigned to (M_H)9/20/2019 11/14/2019 DONE
DetailsMichael Hanson
1st review completed for PLAN MOD - 09/27 plan mod - Jacksons HVAC
CHANGE STATUS TO (ISS)  10/17/2019 DONE
plan mod approved
OVERRIDE  10/16/2019  
Routing - PLAN CHECK10/8/2019 10/16/2019 PASS
DetailsMichael Hanson
Routing Off Site - STRUCTURAL10/8/2019 10/16/2019 PASS
DetailsMichael Hanson
KPFF
Routing - PLAN CHECK10/15/2019 10/16/2019 PASS
DetailsMichael Hanson
1 HOUR PLAN MOD REVIEW FEE
Permit Ready to Issue  10/16/2019 DONE
PLAN MOD
MET office@pnccontractors.com
Need Rev Val for plan mod
Routing - Design Review10/15/2019 10/15/2019 PASS
DetailsKatelyn Menuge
Routing - Design Review10/8/2019 10/10/2019 FAIL
DetailsKatelyn Menuge
Waiting on letter from BRS justifying painting of rtus rather than screening.
Routing - MECHANICAL10/9/2019 10/9/2019 PASS
DetailsTroy James
Routing - MECHANICAL10/1/2019 10/1/2019 FAIL
DetailsTroy James
Need mechanical engineered plans submitted for review. Left voicemail to applicant.
Routing Off Site - STRUCTURAL10/1/2019 10/1/2019 FAIL
DetailsMichael Hanson
See changemark in ePLan for corrections required per KPFF.
Routing - PLAN CHECK10/1/2019 10/1/2019 FAIL
DetailsMichael Hanson
See changemarks from structural, design review, and mechanical for corrections required.
Routing - Design Review9/25/2019 9/25/2019 FAIL
DetailsKatelyn Menuge
Demonstrate how rooftop equipment will be screened from all streets / public view.
Intake Approval  9/23/2019 FAIL
DetailsMichael Hanson
Provide updated engineering for new RTU locations.
Plan Modification Accepted  9/20/2019 DONE
Added (2) new roof top units to building with structural calculations
BLD-Framing/Rough-in8/23/20198/23/20198/23/2019PPASS
DetailsJim Storey
N side wall - Nate Phone #: ###-#### north wall ok/ need si for welds on east wall
Issue PAID IN FULL permit  7/31/2019 DONE
sent email to officePNC
Inspection Record Card- Bld  7/31/2019 DONE
(F) Reprint permit  7/31/2019 DONE
Resend permits because customer did not received email- office@pnccontractors.com
Inspection Record Card- Bld  7/31/2019 DONE
Inspection Record Card- Bld  7/31/2019 DONE
OVERRIDE  7/26/2019  
Permit Ready to Issue  7/26/2019 DONE
all met

NEED RP-met
GC FORM-met
REVISED VALUE-met
PLANS/APPL TAKEN TO FRONT DESK  7/25/2019 DONE
DetailsMichael Hanson
Routing - PLAN CHECK7/17/2019 7/25/2019 PASS
DetailsMichael Hanson
Routing Off Site - STRUCTURAL7/17/2019 7/25/2019 PASS
DetailsMichael Hanson
Approval per Nickolas Pena @ KPFF.
Plan assigned to (M_H)6/19/2019 7/25/2019 DONE
DetailsMichael Hanson
1st review completed - 07/11 #520 L3 ePlan - Jacksons remodel
Routing - Design Review7/18/2019 7/18/2019 PASS
DetailsKatelyn Menuge
DRH19-00113
Route to Impact Fee Review7/10/20197/13/20197/11/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE6/19/20196/19/20197/11/2019 PASS
DetailsMark Scharfen
07.11.2019-Completed fire review. Uploaded rev_fire 07.11.2019.pdf.
Routing Off Site - STRUCTURAL6/19/2019 7/10/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan from KPFF
Routing - PLAN CHECK6/19/2019 7/10/2019 FAIL
DetailsMichael Hanson
See changemark in ePlan for corrections required.
1st review completed  7/10/2019 FAIL
DetailsMichael Hanson
Routing PW Solid Waste6/19/2019 6/21/2019 PASS
DetailsPeter J. McCullough
Routing - Addressing6/19/2019 6/21/2019 PASS
DetailsDoug Chausow
Routing - PLANNING6/19/2019 6/20/2019 PASS
Routing PW Drainage6/19/2019 6/20/2019 PASS
DetailsBrian Murphy
Routing PW Street Lights6/19/2019 6/20/2019 PASS
DetailsTom Marshall
Routing - Design Review6/19/2019 6/20/2019 FAIL
DetailsKatelyn Menuge
Need additional tree at east end of northernmost parking row.
Routing - PUBLIC WORKS6/19/2019 6/19/2019 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment6/19/2019 6/19/2019 PASS
DetailsMichael Zawacki
RP needed, site prep inspection required.
Intake Approval  6/14/2019 PASS
Intake Approval  6/13/2019 FAIL
DetailsBrian McGowan
06/13/19
Please relocate the copyright notation from the electrical sheets.
Thank you,
Intake Approval  6/12/2019 FAIL
DetailsBrian McGowan

Please provide the following documents or information in order to approve your Prescreen;
1. Completed Form #304-
2. Letter from SUEZ concerning fire flow.
3. ESC Waiver Letter or ESC Plans
4. Soils and Geotech Report
5. The original signed and notarized O and M Agreement.
6. Dimensions on the Site Plan showing the building location from the property line.
7. Many of the drawing sheets have your Copyright notation located where the City Stamp will need to be placed. Please relocate this note.
Thank you,
Intake Approval  6/10/2019 FAIL
DetailsBrian McGowan
Please provide the following information or documents for your Prescreen to be approved;
1. A Submittal Checklist must be provided. Provide all the required/requested information and drawings as specified on this form.
2. Only the cover sheet of Form #310 was provided in the Documents and (2) Sheets in the Drawing File. Please provide all the sheets in the Document File.
3. Planning and Zoning Approval Letters must be provided with the submittal.
The Submittal Checklist must be provided with the Prescreen. I cannot verify all the required information without you filling it out as required.

Thank you,
Application received  6/7/2019 DONE
Application submitted via PDS Online on Jun 7 2019 8:25AM
Third Notice 8/16/2020