Print Statement | | | 5/7/2020 | | DONE |
|
|
|
2nd notice
|
Print Statement | | | 4/3/2020 | | DONE |
|
|
|
1st notice
|
Print Statement | | | 2/20/2020 | | DONE |
|
|
|
|
First Notice | | 1/3/2020 | 2/7/2020 | | DONE |
|
|
|
mailed 2-10-20
|
BLD-Final | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PASS |
Mike Jordan
|
|
|
Mike- PLEASE CALL 30 MIN PRIOR FOR SECURITY ACCESS Phone #: ###-####
|
Print Occupancy Form | | | 12/24/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/24/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/23/2019 | | DONE |
|
|
|
this permit was on Final Status but there was no inspection showing that the Final was done, put back in ISS status and schedule the final inspection
|
Plan Reviewer's activity | | | 12/16/2019 | | DONE |
Michael Hanson
|
|
|
Removed plumbing from the required signatures.
|
FIRE-Final Inspection | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.Mike Phone #: ###-####
|
Meeting | | | 10/9/2019 | | DONE |
|
|
|
per Michael Hansen okay to open task on Eplan for client to upload sketch not a plan mod
|
Plan Reviewer's activity | | | 10/9/2019 | | DONE |
Michael Hanson
|
|
|
Met with applicant to discuss the landings and ramps for access to the freezer/refrigerator. We developed a sketch which I have approved as code compliant means of egress. Applicant will upload to eplan and add to the approved drawing set.
|
BLD-Foundation | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | PASS |
Mike Jordan
|
|
|
Please call ahead so I can meet Inspector in parking lot and escort back to site inside the compound at West gate. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band. Ok to proceed. Architect/engineer of record to provide letter stating they are accepting the in place work for the conrete anchors.
|
BLD-Foundation | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PEND |
Mike Jordan
|
|
|
Inspection is for anchoring new cooler to slab. Project is at Ada County Sheriffs compound on Barrister, just inside the automated gate at the West end of parking lot. I have a project meeting this morning in adjacent County office, from 8:45 to 9:45. Hopefully we could have Inspection before, or soon after meeting, so work for the day can proceed. I can meet Inspector in parking lot, and escort him into the site. Thank you. Phone #: ###-#### Inspection requested via web by Gary Band. Anchors have been installed with no special inspection. Engineer of record to accept in place work or determine next steps.
|
BLD-Foundation | 10/1/2019 | 10/1/2019 | 10/1/2019 | A | CANC |
Mike Jordan
|
|
|
Mike any chance we could get this early so we can proceed today? Work is inside the west gate w/ intercom @ elect gate Phone #: ###-#### >> Inspection requested via web by Gary Band Inspection cancelled from web by: Gary Band
|
OVERRIDE | | | 9/26/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/26/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 8/6/2019 | | 9/26/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed - 09/16 #502 L3 ePlan - Sheriff Cooler/Freezer
|
Routing - PLAN CHECK | 9/26/2019 | | 9/26/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - Erosion and Sediment | 9/26/2019 | | 9/26/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Need to list certified RP
|
Permit Ready to Issue | | | 9/26/2019 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Cert of Value
Met
RP
|
Route to Impact Fee Review | 9/16/2019 | 9/19/2019 | 9/23/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/6/2019 | 8/6/2019 | 9/23/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. Standalone freezer and diesel generator installed outside. Inspector to field verify fire extinguisher within 75 foot travel distance.
|
1st review completed | | | 9/16/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 8/6/2019 | | 9/16/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing PW Drainage | 8/7/2019 | | 8/21/2019 | | PASS |
Brian Murphy
|
|
|
existing system see erosion letterand arch.
|
Routing PW Environmental | 8/7/2019 | | 8/14/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 8/6/2019 | | 8/12/2019 | | PASS |
Troy James
|
|
|
Field verify for code compliance.
|
Routing - PLANNING | 8/6/2019 | | 8/8/2019 | | PASS |
Karla Nelson
|
|
|
CZC19-00169
|
Routing - PUBLIC WORKS | 8/6/2019 | | 8/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 8/6/2019 | | PASS |
|
|
|
|
Routing - Design Review | 8/6/2019 | | 8/6/2019 | | PASS |
Katelyn Menuge
|
|
|
CZC19-00169
|
Routing - Addressing | 8/6/2019 | | 8/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 8/5/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
Thank you for the uploaded cooler design plans but the cooler plans are required per the checklist submittal standards to be a minimum 18” x 24” sheet size, required per the ePlan submittal standards to be uploaded as an individual file not as a packet, required per the ePlan submittal standards to have a file naming standard to allow reviewing department know what the file is, and required per the ePlan submittal standards to reserve the bottom right corner for City electronic stamps. (Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block.)
To view the ePlan submittal standards go to https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Intake Approval | | | 6/21/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
1. The engineering calculations are required prior to commencement of review to verify properly sized footing/foundation and reinforcement per design since the majority of the project work hinges on the concrete work the calculations are required. Provide structural calculations for wind, seismic and roof snow loading for the new cooler/freezer structure, calculations required to be stamped/signed/dated by an Idaho licensed engineer.
|
Application received | | | 6/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 11 2019 6:45AM
|
Intake Approval | | | 6/11/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
1. Site specific fire flow at hydrants letter from Suez Water or other public water provider
2. Provide structural calculations for wind, seismic and roof snow loading for the new structure, calculations required to be stamped/signed/dated by an Idaho licensed engineer
3. Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff, form can be found at https://www.cityofboise.org/media/3756/211_verificationlegallot_application.pdf
4. A completed Special Inspection form 310 (see proposed anchor ESR report) stamped/signed/dated by an Idaho licensed engineer
5. Provide information as to what is being stored in the Cooler/Freezer, if food an approved provide Central District Health Department approvals (see checklist)
6. Code Analysis/Building Data on front sheet of plans which includes: Code year, occupancy group(s), construction type(s), floor areas for all floors & building total floor area, building height, fire suppression system (specify NFPA code applicable)
7. Generator specs
8. Cooler/Freezer specs to verify it meets the requirements of the 2015 IECC section 403.2.16
|