BLD-Final | 6/8/2020 | 6/10/2020 | 6/10/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/8/2020 | 6/10/2020 | 6/10/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.44
|
BLD-Energy code compliance | 3/31/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 3/31/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Dave Hannah
|
|
|
ever Phone #: ###-####082
|
BLD-Other | 3/9/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Dave Hannah
|
|
|
sheetrock soffits ok
|
BLD-Foundation | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 11/5/2019 | 11/6/2019 | 11/6/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 11/6/2019 | 11/6/2019 | 11/6/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 10/23/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/24/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 6/12/2019 | 6/12/2019 | 6/24/2019 | | DONE |
Rob Patrick
|
|
|
06/25 sfd L1 ePlan
|
Routing - PLAN CHECK | 6/12/2019 | | 6/24/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 6/24/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2019 | | DONE |
Rob Patrick
|
|
|
|
Override - Parcel Holds | | | 6/24/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 6/24/2019 | | DONE |
|
|
|
|
Routing - Addressing | 6/12/2019 | | 6/14/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 6/12/2019 | | 6/14/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/12/2019 | 6/15/2019 | 6/13/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 6/12/2019 | 6/12/2019 | 6/13/2019 | | PASS |
Lee G Meredith
|
|
|
06/26-2566 E Warm Springs ePlan 402
Sprinklers are not required.
|
Routing - PUBLIC WORKS | 6/12/2019 | | 6/13/2019 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 6/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 12 2019 2:00PM
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/12/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 6/12/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/12/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 6/12/2019 | | 6/12/2019 | | PASS |
Sue Cummings
|
|
|
|