Letter of compliance/Occupancy | | | 8/5/2019 | | DONE |
|
|
|
|
BLD-Final | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Dave Hannah
|
|
|
Laren Phone #: ###-####
|
FIRE-Final Inspection | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, outlets for VR units shunt during fire alarm activation, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
|
BLD-Final | 7/31/2019 | 8/1/2019 | 8/1/2019 | P | CANC |
Tell Riley
|
|
|
Leren Phone #: ###-####//cancel per Leren//need to pass fire final//
|
FIRE-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | FAIL |
Mark Scharfen
|
|
|
E-lights/extinguisher in place. Tested interface for shunt with Protex on site. Manually turning on relay did shunt the breaker but did not work in normal operation. Told Leren and Protex that a fire alarm permit would need to be pulled and proof of a propper pretest before building or fire alarm final is to be called in again.
Leren Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 8/1/2019 | | DONE |
|
|
|
Dave H. doc final accidently per Mark Scharfen change status to ISS
|
DOC - Permit Finaled | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | PASS |
Dave Hannah
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/9/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/1/2019 | | 7/1/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/1/2019 | | DONE |
|
|
|
MET
Need GC
Need Rev cert of val
|
Plan assigned to (M_H) | 6/24/2019 | | 7/1/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed - 06/25 #518 L1 ePlan - BlackBox VR
|
Route to Impact Fee Review | 6/24/2019 | 6/27/2019 | 6/25/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 6/19/2019 | 6/19/2019 | 6/24/2019 | | DEFR |
Javier Guzman
|
|
|
06/25 L1 BlackBox VR ePlan
|
Routing - PLAN CHECK | 6/19/2019 | | 6/24/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
1st review completed | | | 6/24/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Intake Approval | | | 6/19/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 6/19/2019 | | 6/19/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Addressing | 6/19/2019 | | 6/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 6/14/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 14 2019 3:38PM
|