BLD-Aging Inspection | 1/31/2020 | 1/31/2020 | 2/4/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 1/30/2020 | 1/30/2020 | 2/4/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Dave Hannah
|
|
|
Todd Phone #: ###-####
|
BLD-Framing/Rough-in | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Dave Hannah
|
|
|
Todd Phone #: ###-####
|
BLD-Footing | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Dave Hannah
|
|
|
TODD Phone #: ###-####
|
PubWorks Subgrade Approval | 7/24/2019 | 7/24/2019 | 7/24/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 6/25/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/19/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/17/2019 | 6/17/2019 | 6/19/2019 | | PASS |
Josh Bogle
|
|
|
6/21 addition, paper
|
Routing - PLAN CHECK | 6/17/2019 | | 6/19/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/19/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 6/19/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 6/19/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 6/19/2019 | | DONE |
|
|
|
Need RP
|
Routing - Erosion and Sediment | 6/17/2019 | | 6/18/2019 | | PASS |
Michael Zawacki
|
|
|
Waiver approved
|
Routing Walk-In (Zoning) | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Josh Bogle
|
|
|
took in as a level 2 to route to ESC (waiting on waiver letter)
|
Routing PW Grading-Hillside | 6/17/2019 | | 6/17/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Application received | | 6/17/2019 | | | |
|
|
|
|