First Notice | 8/16/2019 | 8/16/2019 | 9/19/2019 | | DONE |
Mike Jordan
|
|
|
mailed 9-20-19
|
BLD-Final | 8/15/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
Don ###-####
|
DOC - Permit Finaled | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler modifications, are complete, no fire alarm modifications, fire extinguisher will be mounted in discussed location. Final life fire safety inspection for area of work complete.
Don ###-####
|
BLD-Framing/Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Brandon Shaw
|
|
|
call for access- Mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/12/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/11/2019 | | DONE |
Michael Hanson
|
|
|
Reviewed occupancy type decision with Javier Guzman. We decided due to the definition of an M occupancy that this project fit better as an M as opposed to an S-1.
|
Routing - PLAN CHECK | 7/11/2019 | | 7/11/2019 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/11/2019 | | DONE |
|
|
|
emailed kramirez@lirasprestigecompanies.com fees due
all MET- NEED
GC FORM
REVISED VALUE
|
Plan assigned to (M_H) | 6/25/2019 | | 7/11/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed - 07/08 #518 L2 ePlan - Macy's
|
Route to Impact Fee Review | 7/8/2019 | 7/11/2019 | 7/9/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/25/2019 | 6/25/2019 | 7/8/2019 | | PASS |
Mark Scharfen
|
|
|
07.08.2019-Completed fire code review. Made notations on plans. No report uploaded.
|
Routing - PLAN CHECK | 6/25/2019 | | 7/8/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
1st review completed | | | 7/8/2019 | | FAIL |
Michael Hanson
|
|
|
|
Plan Reviewer's activity | | | 6/27/2019 | | DONE |
Michael Hanson
|
|
|
Returned to applicant per phone conversation to resubmit documents affected by the demo only permit pulled on the T.I..
|
Routing - Addressing | 6/25/2019 | | 6/26/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2019 | | 6/26/2019 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Intake Approval | | | 6/25/2019 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by M_H.
|
Plan Reviewer's activity | | | 6/24/2019 | | DONE |
Michael Hanson
|
|
|
GC CALLED AND IS CONSIDERING EARLY START DEMO
|
Intake Approval | | | 6/20/2019 | | FAIL |
Michael Hanson
|
|
|
Please provide approval letter from Boise Town Square Mall for floor plan modifications.
Include information regarding existing smoke control system and how it is affected and/or maintained.
Include information regarding bulkhead that cannot be penetrated or attached to.
Provide wall bracing detail.
|
Application received | | | 6/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 18 2019 9:57AM
|