BLD-Final | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Mike Jordan
|
|
|
Call for access- Gari Phone #: ###-####
|
DOC - Permit Finaled | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | NR |
Mike Jordan
|
|
|
Gari Phone #: ###-####. All framing issues not yet corrected.
|
BLD-Energy code compliance | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | NR |
Mike Jordan
|
|
|
Gari Phone #: ###-####
|
BLD-Framing/Rough-in | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | FAIL |
Mike Jordan
|
|
|
Gotti Phone #: ###-####. Provide additional stud under G01 2ply truss in garage, west side. Provide the continous bearing onA04 truss, west end. foam electrical wires through top plate at barrel vauld, main entry. Replace cut 2x6 stud in back portal frame. Correction notice posted. ok to insulate.
|
BLD-Framing/Rough-in | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | FAIL |
Mike Jordan
|
|
|
Gadi Phone #: ###-####. Provide the correct truss engineering. Recall framing inspection.
|
BLD-Wall Bracing | 9/4/2019 | 9/5/2019 | 9/5/2019 | A | PASS |
Mike Jordan
|
|
|
Gari Phone #: ###-####
|
BLD-Wall Bracing | 9/3/2019 | 9/3/2019 | 9/3/2019 | P | FAIL |
Tell Riley
|
|
|
Gari Phone #: ###-####//portal frames do not match engineering//details on engineering are not readable//please see correction notice onsite//
|
BLD-Foundation | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | PASS |
Mike Jordan
|
|
|
Ricardo Phone #: ###-####
|
BLD-Footing | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | NR |
Mike Jordan
|
|
|
|
BLD-Footing | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 7/22/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/22/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/27/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/27/2019 | 6/27/2019 | 6/27/2019 | | PASS |
Josh Bogle
|
|
|
7/02 sfd L1 ePlan
|
Plan assigned to (J_N) | 6/19/2019 | 6/19/2019 | 6/27/2019 | | DEFR |
Jenny Nelson
|
|
|
07/02 sfd L1 ePlan
|
Routing - PLAN CHECK | 6/19/2019 | | 6/27/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/27/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 6/27/2019 | | DONE |
|
|
|
Met
|
Routing - MECHANICAL | 6/19/2019 | | 6/21/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/19/2019 | 6/22/2019 | 6/20/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 6/19/2019 | | 6/20/2019 | | PASS |
Sue Cummings
|
|
|
Maximum width of driveway is 33 ft. in the front setback
|
Routing - PUBLIC WORKS | 6/19/2019 | | 6/20/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/19/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/19/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/19/2019 | | DONE |
|
|
|
|
Routing - Addressing | 6/19/2019 | | 6/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 6/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 18 2019 3:59PM
|