BLD-Final | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | PASS |
Jim Storey
|
|
|
Jason Phone #: ###-####
|
DOC - Permit Finaled | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Jim Storey
|
|
|
JASON Phone #: ###-####
|
BLD-Wall Bracing | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Jim Storey
|
|
|
reinspect - Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Jim Storey
|
|
|
reinspect - Jason Phone #: ###-####
|
BLD-Wall Bracing | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | FAIL |
Jim Storey
|
|
|
shear // Jason Phone #: ###-####
|
BLD-Wall Bracing | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Jim Storey
|
|
|
shear // Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Jim Storey
|
|
|
Jason Phone #: ###-####
|
BLD-Footing | 8/5/2019 | 8/6/2019 | 8/6/2019 | A | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-#### compaction report good ok to place.
|
BLD-Footing | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | NR |
Jim Storey
|
|
|
Matt Phone #: ###-#### need compaction report
|
Issue PAID IN FULL permit | | | 7/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/10/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 6/20/2019 | 6/20/2019 | 7/10/2019 | | DONE |
Rob Patrick
|
|
|
07/03 sfd ePlan...07/01 Failed; need braced wall engineering
|
Routing - PLAN CHECK | 7/10/2019 | | 7/10/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 7/10/2019 | | DONE |
|
|
|
|
1st review completed | | | 7/1/2019 | | FAIL |
Rob Patrick
|
|
|
Need to provide engineering for braced walls
|
Routing - PLAN CHECK | 6/20/2019 | | 7/1/2019 | | FAIL |
Rob Patrick
|
|
|
|
Route to Impact Fee Review | 6/20/2019 | 6/23/2019 | 6/21/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/20/2019 | | 6/21/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/20/2019 | | 6/21/2019 | | PASS |
Sue Cummings
|
|
|
If the driveway is being replaced, it needs to comply with current Code. No more than 33 ft. wide in the front setback
|
Routing - Addressing | 6/20/2019 | | 6/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 6/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 20 2019 2:38PM
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2019 | | 6/20/2019 | | PASS |
Angela Hardy
|
|
|
|