BLD-Final | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Mike Jordan
|
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 2/12/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved.
|
BLD-Final | 2/4/2020 | 2/4/2020 | 2/4/2020 | P | FAIL |
Mike Jordan
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Provide handrail for front stairs. Complete fill and grading. Clean up trash from crawl spcae and complte vapor barrier.
|
BLD-Energy code compliance | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD-Energy code compliance | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD-Framing/Rough-in | 12/2/2019 | 12/3/2019 | 12/3/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Nail D4G 2ply truss per the engineering. Provide purlins on top chords of B3 and B4 trusses at overbuild were roof sheathing has been left off. Ok to insulate. Correction notice posted.
|
BLD-Wall Bracing | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 11/1/2019 | 11/4/2019 | 11/4/2019 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 10/31/2019 | 11/1/2019 | 11/1/2019 | P | PART |
Mike Jordan
|
|
|
dane Phone #: ###-####
|
Routing - MECHANICAL | 10/17/2019 | | 10/18/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Plan Modification Accepted | | | 10/17/2019 | | DONE |
|
|
|
plan mod for manual J
|
Inspection Record Card- Bld | | | 10/2/2019 | | DONE |
|
|
|
attached sign off card in e plan approved docs
|
Issue PAID IN FULL permit | | | 10/2/2019 | | DONE |
|
|
|
emailed permitting@cbhhomes.com to sign permits and send back
|
OVERRIDE | | | 7/3/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 6/21/2019 | 6/21/2019 | 7/3/2019 | | DONE |
Rob Patrick
|
|
|
07/04 sfd L1 ePlan
|
Routing - PLAN CHECK | 6/21/2019 | | 7/3/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 7/3/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 7/3/2019 | | DONE |
|
|
|
met
|
Route to Impact Fee Review | 6/21/2019 | 6/24/2019 | 6/24/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 6/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 21 2019 7:11AM
|
Plans ACCEPTED BY PLAN TECH | | | 6/21/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/21/2019 | | PASS |
|
|
|
|
Routing - MECHANICAL | 6/21/2019 | | 6/21/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/21/2019 | | 6/21/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/21/2019 | | 6/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/21/2019 | | 6/21/2019 | | PASS |
Angela Hardy
|
|
|
|