BLD-Other | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PEND |
Tony Young
|
|
|
Where are we on obtaining final ?// contractor will have permit changed to owners name,, owner will finish
|
BLD-Conference | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | FAIL |
Tony Young
|
|
|
Status?
|
BLD-Energy code compliance | 10/17/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Mike Jordan
|
|
|
dan- Phone #: ###-####
|
BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-####,, ok to insulate after minor corrections
|
BLD-Energy code compliance | 10/11/2019 | 10/14/2019 | 10/14/2019 | P | PART |
Tony Young
|
|
|
Dan Phone #: ###-####,, seal pack ok,, minor frame corrections on strapping, nailing hangers, support of cut existing joist
|
BLD-Wall Bracing | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####
|
BLD-Foundation | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Dave Hannah
|
|
|
Dan Phone #: ###-####
|
BLD-Footing | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 7/18/2019 | 7/18/2019 | 7/18/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/17/2019 | 7/17/2019 | 7/17/2019 | P | NR |
Brandon Shaw
|
|
|
Need Geo soil subgrade submitted and approved by PW...
|
BLD-Footing | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PEND |
Tony Young
|
|
|
Dan Phone #: ###-####,, needs soils approval,, then ok
|
OVERRIDE | | | 7/3/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/21/2019 | 6/21/2019 | 7/3/2019 | | PASS |
Josh Bogle
|
|
|
06/27 addition, paper - 1st done
|
Issue PAID IN FULL permit | | | 7/3/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/3/2019 | | 7/3/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 7/3/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/3/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 7/3/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/2/2019 | | DONE |
|
|
|
Three copies of plans A7 and A7.2 taken to josh
|
Routing Walk-In (BLD) | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | FAIL |
Josh Bogle
|
|
|
to submit additional plans
|
Routing Walk-In (BLD) | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | PASS |
Josh Bogle
|
|
|
applicant brough in ESC waiver & updated Geotech - took to Hillside
|
1st review completed | | | 6/27/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 6/21/2019 | | 6/27/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - Erosion and Sediment | 6/27/2019 | | 6/27/2019 | | PASS |
Michael Zawacki
|
|
|
Waiver approved
|
Routing - PLAN CHECK | 6/21/2019 | | 6/27/2019 | | FAIL |
Josh Bogle
|
|
|
missing WUI, Section views - engineering doesn't match
|
Routing Walk-In (Zoning) | 6/21/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Ethan Mansfield
|
|
|
kitchen and dining expansion; does not expand existing building footprint.
|
Routing Walk-In (BLD) | 6/21/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Josh Bogle
|
|
|
took in as a level two, routed to Hillside and ESC
|
Application received | | 6/21/2019 | | | |
|
|
|
|