Permit Information
Permit NumberBLD19-02311
StatusIssued
Name DAN HEMMER CONSTRUCTION INC
Site Address 401 W HIGHLAND VIEW DR
Project NameHelling Addition
Customer Number 
ePlanReviewNo
Description
HILLSIDE - WUI - Permit for a 455sq' two level addition. On the main level, the project expands and reconfigures the Kitchen/Dining area. On the upper level, the project expands and reconfigures two Bedrooms and add two Full Baths. All work per plans, notations, attachments, engineerings, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Other6/3/20206/4/20206/4/2020APEND
DetailsTony Young
Where are we on obtaining final ?// contractor will have permit changed to owners name,, owner will finish
BLD-Conference5/15/20205/18/20205/18/2020AFAIL
DetailsTony Young
Status?
BLD-Energy code compliance10/17/201910/18/201910/18/2019PPASS
DetailsMike Jordan
dan- Phone #: ###-####
BLD-Framing/Rough-in10/14/201910/15/201910/15/2019APART
DetailsTony Young
Dan Phone #: ###-####,, ok to insulate after minor corrections
BLD-Energy code compliance10/11/201910/14/201910/14/2019PPART
DetailsTony Young
Dan Phone #: ###-####,, seal pack ok,, minor frame corrections on strapping, nailing hangers, support of cut existing joist
BLD-Wall Bracing8/23/20198/23/20198/23/2019PPASS
DetailsTony Young
Bob Phone #: ###-####
BLD-Foundation7/22/20197/23/20197/23/2019APASS
DetailsDave Hannah
Dan Phone #: ###-####
BLD-Footing7/18/20197/18/20197/18/2019PPASS
DetailsBrandon Shaw
Work in progress...
PubWorks Subgrade Approval7/18/20197/18/20197/18/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

BLD-Footing7/17/20197/17/20197/17/2019PNR
DetailsBrandon Shaw
Need Geo soil subgrade submitted and approved by PW...
BLD-Footing7/16/20197/16/20197/16/2019PPEND
DetailsTony Young
Dan Phone #: ###-####,, needs soils approval,, then ok
OVERRIDE  7/3/2019  
Plan assigned to (JAB) Josh6/21/20196/21/20197/3/2019 PASS
DetailsJosh Bogle
06/27 addition, paper - 1st done
Issue PAID IN FULL permit  7/3/2019 DONE
Routing - PLAN CHECK7/3/2019 7/3/2019 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  7/3/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  7/3/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  7/3/2019 DONE
DetailsJosh Bogle
Permit Ready to Issue  7/3/2019 DONE
Plan resubmittals received  7/2/2019 DONE
Three copies of plans A7 and A7.2 taken to josh
Routing Walk-In (BLD)7/1/20197/1/20197/1/2019PFAIL
DetailsJosh Bogle
to submit additional plans
Routing Walk-In (BLD)6/27/20196/27/20196/27/2019PPASS
DetailsJosh Bogle
applicant brough in ESC waiver & updated Geotech - took to Hillside
1st review completed  6/27/2019 FAIL
DetailsJosh Bogle
Routing PW Grading-Hillside6/21/2019 6/27/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Routing - Erosion and Sediment6/27/2019 6/27/2019 PASS
DetailsMichael Zawacki
Waiver approved
Routing - PLAN CHECK6/21/2019 6/27/2019 FAIL
DetailsJosh Bogle
missing WUI, Section views - engineering doesn't match
Routing Walk-In (Zoning)6/21/20196/21/20196/21/2019APASS
DetailsEthan Mansfield
kitchen and dining expansion; does not expand existing building footprint.
Routing Walk-In (BLD)6/21/20196/21/20196/21/2019APASS
DetailsJosh Bogle
took in as a level two, routed to Hillside and ESC
Application received 6/21/2019