Permit Information
Permit NumberBLD19-02339
StatusIssued
Name ESI
Site Address 1100 W IDAHO ST
Project Name11th & Idaho - Shell & Core
Customer NumberESC19-00779
ePlanReviewYes
Description
(11TH AND IDAHO) (SHELL & CORE) **Project Management- Ron Hill **PLAN MOD #2 (7/22/20) REVISED DETAILS FOR 2HR WALL TERMINATION AT EXTERIOR WEST WALL **PLAN MOD (7/7/20) REVISED 2_HR WALL FROM U411 to W440. **NO OCCUPANCY ALLOWED UNDER THIS PERMIT. TENANT SHALL APPLY FOR CERTIFICATE OF OCCUPANCY FOR EACH TENANT PRIOR TO OCCUPYING ANY FLOOR OR ROOFTOP. ** All tenant improvements are required to provide commissioning upon buildout per 2015 IECC. (DRH18-00260) (DRH19-00228) This building is type I-B construction and is fully fire sprinklered because it is a high-rise. Permit is to complete the envelope and tenant improvement phase (Package II) for a 9-story shell & core office building with an occupied roof and mechanical penthouse on the roof level. The building has a total floor area of about 172,610 square feet (approximately 18,990 square feet 1st story, approximately 19,500 square feet second story, and 19,160 square feet 3rd through 9th story). The building has an occupied roof that is not included in the building area. The concrete and structural steel phase was done under permit BLD19-02122 (Package I). Special Inspection is required for concrete, steel (including welding and bolting), fire-resistance coatings, fire stopping, anchors post-installed in hardened concrete, and smoke control system and was provided under Package I. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A separate permit is required for the fire sprinkler system and shall comply with NFPA 13. The fire alarm system requires a separate permit and is required to comply with NFPA 72, including the smoke detection system, as regulated by the Fire Department. Prior to the issuance of a Certificate of Completion, a commissioning report for the shell and core shall be submitted to and accepted by the code official. See form #308 for system commissioning responsibilities checklist. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover8/11/20208/12/20208/12/2020APASS
DetailsJim Storey
Please come reinspect 4th floor bathroom for lid cover. 5th and 6th floor for lid cover in bathrooms. Phone #: ###-#### Inspection requested via web by Andy Pense east and main shaft assemblies and penatrations ok// 4 and 5 th ceillings ok shaft protection ok. rfi for coloum protction empeded by horrazontal tube steel must meet 2 hr struc. prorection.
BLD-Wall cover8/10/20208/10/20208/10/2020PPART
DetailsDave Hannah
please come inspect the 3rd and 4th floor bathrooms for lid cover. Phone #: ###-#### Inspection requested via web by Andy Pense ok to cover lids
BLD-Wall cover8/4/20208/4/20208/4/2020PNR
DetailsDave Hannah
Please come inspect mechanical shaft on the East. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover8/3/20208/3/20208/3/2020PPART
DetailsDave Hannah
Please come verify work complete to cover stair 2 first floor 2 hour. First floor loggia for cover in the lobby as well.
Thank you. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover7/29/20207/29/20207/29/2020APASS
DetailsDave Hannah
Please come inspect the ceiling of the North notch. Please come inspect the 3rd and 4th floors for progress and ceiling cover. Progress on the West wall first floor. Progress on stair 2, 2 hour assembly. Phone #: ###-#### Inspection requested via web by Andy Pense
Permit Ready to Issue  7/23/2020 DONE
Plan Mod
CHANGE STATUS TO (ISS)  7/23/2020 DONE
BLD-Other7/22/20207/22/20207/22/2020PPASS
DetailsJim Storey
*Screened* Interior wall cover, Andy Phone #: ###-#### restarms floor penatrations and walls 5 and 6 ok to cover// reviewed stair 2# penatrations ok wip
Plan assigned to (Joe)7/16/20207/16/20207/22/2020 PASS
DetailsJoe Bruce
Plan Mod #2
Routing - PLAN CHECK7/21/2020 7/22/2020 PASS
DetailsJoe Bruce
Plan Mod #2
BLD-Wall cover7/20/20207/21/20207/21/2020APASS
DetailsMike Jordan
Andy *screened* Phone #: ###-####. Elevator shaft walls for cars 3 and 4 on 10th. floor. Fire proofing patch back on west coloumn north notch. Stair 2 shaft walls floor 6 to 10. main mech shaft floor 3.
BLD-Wall cover7/14/20207/15/20207/17/2020APART
DetailsDave Hannah
Please come inspect the following; Stair 1 and stair 2 for cover, 2 Hr. electrical box in the communication room south shaft wall. North notch East column all the way up to level 10. Fire caulk in the bathrooms 2-3 at the floors, main shaft for cover.
Thanks, Please call if you have any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
Plan Modification Accepted  7/16/2020 DONE
Plan Mod #2 - Revisions to 2hr separation wall. Sheets affected A11-01 & A61-05
Plan Reviewer's activity  7/16/2020 DONE
DetailsJoe Bruce
Regarding the plan mod #2 - Please provide the licensed design professional architect stamp and signature on the revised plan mod sheets.
CHANGE STATUS TO (ISS)  7/13/2020 DONE
Plan assigned to (Joe)7/1/20207/1/20207/7/2020 PASS
DetailsJoe Bruce
Routing - PLAN CHECK7/7/2020 7/7/2020 PASS
DetailsJoe Bruce
Plan mod passed - Changed 2-hour wall from U411 to W440
Permit Ready to Issue  7/7/2020 DONE
plan mod approved
DO NOT RE ISSUE
Route to Impact Fee Review7/1/20207/4/20207/6/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
Plan Modification Accepted  7/1/2020 DONE
Adding an additional UL assembly for the construction of a 2hr- wall
BLD-Wall cover6/30/20206/30/20206/30/2020ADONE
DetailsDave Hannah
Please come and inspect the South notch bay East column.
Thanks. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in6/30/20206/30/20206/30/2020PPART
DetailsDave Hannah
column east end of south notch ok to cover
BLD-Wall cover6/26/20206/26/20206/26/2020PPART
DetailsJim Storey
Please come inspect the South notch East side for cover. Contact Andy Pense ###-#### thanks Phone #: ###-#### Inspection requested via web by Andy Pense web patch ok idaho st flange stil nees coverage of fireproofing.
BLD-Wall cover6/24/20206/24/20206/24/2020APART
DetailsDave Hannah
Please come inspect the first floor walls for cover. Inspect the 10th floor shaft liner. Phone #: ###-#### Inspection requested via web by Andy Pense first floor north corrador ok
BLD-Wall cover6/15/20206/16/20206/16/2020APART
DetailsDave Hannah
Please come inspect the South Notch East wall 2-9. Call Andy with any questions. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover6/11/20206/12/20206/12/2020APEND
DetailsDave Hannah
Come inspect the south west notch framing for cover. Thanks. Call Andy Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover6/4/20206/5/20206/5/2020APASS
DetailsDave Hannah
Please come inspect the insulation in the electrical room level 1. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in6/3/20206/3/20206/4/2020PPASS
DetailsDave Hannah
Penthouse framing inspection to cover. Please get with Mike Koci Or Andy Pense. Thanks Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Framing/Rough-in5/19/20205/20/20205/20/2020APASS
DetailsDave Hannah
Please come inspect the shaft wall in the elevator pit 3,4. Also South exterior framing for cover. Phone #: ###-#### Inspection requested via web by Andy Pense
BLD-Wall cover5/18/20205/18/20205/18/2020PPASS
DetailsJim Storey
west cuttin wall minrial wool ok to cover.
BLD-Framing/Rough-in3/19/20203/19/20203/19/2020PPART
DetailsDave Hannah
Inspect NE section of exterior framing on 3,4 ; 5th flrs. Please call when onsite. Thanks! Phone #: ###-#### Inspection requested via web by Mike Koci section on north side ok
FIRE-Conference2/20/20202/20/20202/20/2020ADONE
DetailsJim Page
Temporary standpipe has been placed and is in service.
FIRE-Conference2/13/20202/13/20202/13/2020ADONE
DetailsJim Page
Discussed temporary standpipe approximately 2 weeks ago with site foreman with ESI, temp standpipe has net been installed as of this entry, per section 3313.1 of the 2015 IFC states that a temporary standpipe is required when construction reaches 40 feet, project is past the 40 foot height measurement. ESI superintendent has been notified that the temporary standpipe needs to be installed and operational by 21FEB2020 or a stop work will be placed on project until temporary standpipe is installed. This has been discussed with and supported by Joe Bruce, Fire section supervisor as well as Romeo Gervais, Boise City Fire Marshall.
Issue PAID IN FULL permit  11/13/2019 DONE
Inspection Record Card- Bld  11/13/2019 DONE
Routing - FIRE10/25/201910/25/201910/30/2019 PASS
DetailsErika Akin
Attached comments to case
Plan assigned to (JHB)7/9/20197/9/201910/30/2019 PASS
DetailsJoe Bruce
(2nd Rev Comp) 08/19 (502) 11th & Idaho, ePlan **Project Management Ron Hill**
PLANS/APPL TAKEN TO FRONT DESK  10/30/2019 DONE
Permit Ready to Issue  10/30/2019 DONE
MET
Routing - PLAN CHECK10/25/2019 10/28/2019 PASS
DetailsJoe Bruce
See plan review report uploaded on 10.28.19 **JHB**
Routing PW Street Lights10/25/2019 10/25/2019 PASS
DetailsTom Marshall
Plan resubmittals received  10/25/2019 DONE
DetailsJoe Bruce
Plan resubmittals received  10/24/2019 FAIL
DetailsJoe Bruce
Received resubmittal in ePlan from Devin on 10/23/19.
Plan resubmittals requested  10/24/2019 DONE
DetailsJoe Bruce
Please correct the following items before we can process your resubmittal:

1) The following resubmitted pages are missing the registered design professional stamp & signature: G00-01, A11-01, A11-02, A11-03, A12-01, A12-02, A12-03, A30-02, A61-04, E31-04, E31-05. Please resubmit and provide the stamp/signature by the architect and/or engineer on these pages.

2) Form #308 is missing the owner's (Scott Schoenherr) signature on the 1st page. Please have Scott sign and date this form to acknowledge the commissioning agency for the IECC.
Routing - FIRE10/4/201910/4/201910/18/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - Design Review10/4/2019 10/17/2019 PASS
DetailsJosh Wilson
Routing - PLAN CHECK10/4/2019 10/14/2019 FAIL
DetailsJoe Bruce
Routing PW Street Lights10/4/2019 10/7/2019 PASS
DetailsTom Marshall
Routing PW Sewer Design10/4/2019 10/4/2019 PASS
DetailsDeAnn Brown
Sewer connection approved under BLD19-02122. Current application is only for interior plumbing changes.
Routing - FIRE7/9/20197/9/20198/19/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK7/9/2019 8/19/2019 FAIL
DetailsJoe Bruce
Plan Review Report contains comments that require a resubmittal.
Plan resubmittals requested  8/19/2019 DONE
DetailsJoe Bruce
1st review completed  8/19/2019 DONE
DetailsJoe Bruce
Routing Off Site - STRUCTURAL7/9/2019 8/13/2019 PASS
DetailsJoe Bruce
Structural Review under BLD19-02122
Routing - MECHANICAL7/9/2019 7/19/2019 PASS
DetailsTroy James
Routing - Design Review7/9/2019 7/19/2019 FAIL
DetailsJosh Wilson
Provide copy of executed license agreement with ACHD for canopies within R.O.W.
Routing PW Sewer Design7/10/2019 7/18/2019 FAIL
DetailsDeAnn Brown
Please provide site civil plans that show sewer connection to the public sewer system.
Routing - PLANNING7/9/2019 7/17/2019 PASS
DetailsNicolette Womack
Routing PW Environmental7/10/2019 7/16/2019 PASS
DetailsRick Christenson
Routing PW Solid Waste7/10/2019 7/12/2019 PASS
DetailsEvan Carpenter
Routing - PLUMBING7/9/2019 7/12/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing PW Drainage7/10/2019 7/11/2019 PASS
DetailsBrian Murphy
DRAINAGE REVIEW UNDER FOUNDATION PERMIT
Routing PW Geothermal7/10/2019 7/11/2019 PASS
DetailsJon R. Gunnerson
Contact PW to connect onto geothermal heating district. Jon Gunnerson ###-####
Routing PW Street Lights7/10/2019 7/10/2019 FAIL
DetailsTom Marshall
Routing - Addressing7/9/2019 7/10/2019 PASS
DetailsDoug Chausow
Address changed: 1104 W Idaho St
7/17 Address changed: 1100 W Idaho St
Routing - PUBLIC WORKS7/9/2019 7/10/2019 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment7/9/2019 7/10/2019 PASS
DetailsMichael Zawacki
Please refer to ESC19-00779 issued with foundation and super structure permit.
Intake Approval  7/9/2019 PASS
DetailsCarl Westfall
Prescreen approved by CJW
Plan Reviewer's activity  7/8/2019 PASS
Plan intake review approved
Intake Approval  6/26/2019 FAIL
(6-26-19) Refer to the circled items in the plan intake checklist. Resolve each item as directed. CJW
Application received  6/24/2019 DONE
Application submitted via PDS Online on Jun 24 2019 11:31AM
BLD-Wall cover8/13/20208/14/2020 A 
DetailsDave Hannah
Please come inspect the 6th floor for lid for cover. Inspect framing on stair 1 and stair 2. Inspect mechanical shaft liner for cover levels 7-8-9. Inspect the lobby soft for cover, Electrical is in on the East side of the curtain wall lobby. Phone #: ###-#### >> Inspection requested via web by Andy Pense