BLD-Final | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | DEFR |
Brandon Shaw
|
|
|
Need electrical rough/final... No other issues...
|
BLD-Framing/Rough-in | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Jim Storey
|
|
|
call 30 mins ahead- Justin Phone #: ###-#### pending trades to begin work.
|
BLD-Footing | 7/23/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Jim Storey
|
|
|
Justin Phone #: ###-####
|
Telephone call | | | 7/10/2019 | | DONE |
|
|
|
emailed GC stating that they did not need to pay the ESC fee (per Josh) and to email Tisha to request a refund.
|
Issue PAID IN FULL permit | | | 7/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 7/2/2019 | 7/2/2019 | 7/5/2019 | | PASS |
Josh Bogle
|
|
|
07/08 remodel, ePlan
|
Routing - PLAN CHECK | 7/2/2019 | | 7/5/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 7/5/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 7/5/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 7/2/2019 | | 7/2/2019 | | PASS |
Ethan Mansfield
|
|
|
Height of garage to midline of roof cannot exceed 22 feet.
|
Intake Approval | | | 7/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/2/2019 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | | 6/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 24 2019 12:02PM
|
Intake Approval | | | 6/24/2019 | | FAIL |
|
|
|
Drawings need to be changed so the orientation is facing the correct way. Landscape style. Also you need to upload the drawings individually. Once that is done and you sign off on your task we will do the prescreen.
|