BLD-Final | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | DONE |
Tony Young
|
|
|
Justin *screened8 Phone #: ###-####// no electrical at this point
|
DOC - Permit Finaled | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Footing | 3/23/2020 | 3/25/2020 | 3/25/2020 | A | PASS |
Dave Hannah
|
|
|
call ahead to meet- Andrew Phone #: ###-####
|
BLD-Wall Bracing | 1/30/2020 | 1/31/2020 | 1/31/2020 | A | CANC |
Dave Hannah
|
|
|
early- Jerry Phone #: ###-####
|
BLD-Footing | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PART |
Tony Young
|
|
|
Dave Phone #: ###-####,, post holes.. work in progress,, ok
|
Issue PAID IN FULL permit | | | 7/5/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 7/3/2019 | 7/3/2019 | 7/3/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/3/2019 | | DONE |
|
|
|
|
Telephone call | | | 7/3/2019 | | DONE |
|
|
|
called Justin to let know permit is ready and how much is owed
|
Routing - PLAN CHECK | 7/3/2019 | | 7/3/2019 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/3/2019 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/3/2019 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 7/3/2019 | | DONE |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 7/3/2019 | | |
Brian McGowan
|
|
|
Spoke with Carl about the window and door detail not showing the typical king studs, timmers, sill or header on the Details knowing they are not typical for pole barn framing. He said it is not vital to the structure and safety of the pole barn and to let it go, they will catch it in the field when framing.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2019 | | DONE |
Brian McGowan
|
|
|
|
Plan resubmittals received | | | 7/2/2019 | | DONE |
|
|
|
2 packets of structural cal, 2 sets of structural plans, site plan and planning and development services approval letter.
|
Routing Walk-In (BLD) | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | CANC |
Josh Bogle
|
|
|
no contact with applicant
|
Routing Walk-In (Zoning) | 6/27/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
KayCee Babb
|
|
|
CZC18-00252
|
Routing Walk-In (BLD) | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | FAIL |
Brian McGowan
|
|
|
Engineering calculations need to specify 2015 IRC or 2015 IBC
|
Routing - PLAN CHECK | 6/27/2019 | | 6/27/2019 | | FAIL |
Brian McGowan
|
|
|
Engineering calculations need to specify 2015 IRC or 2015 IBC
|
1st review completed | | | 6/27/2019 | | DONE |
Brian McGowan
|
|
|
Engineering calculations need to specify 2015 IRC or 2015 IBC
|
Application received | | 6/27/2019 | | | |
|
|
|
|