BLD-Final | 10/31/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Mike Jordan
|
|
|
Mike,
Troy should have his final done by noon. Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns. Ok for perm occ.
|
FIRE-Final Inspection | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Provide sticker as discussed prior to the building inspection.
requested via web by Todd Kurns
|
BLD-Ceiling Grid Inspection | 10/24/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Mike Jordan
|
|
|
Mike,
Call me for access to space. Electrical is inspected and HVAC should be this morning before you do grid this afternoon. Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
Print Occupancy Form | | | 10/24/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | NR |
Mike Jordan
|
|
|
Mike,
We r good to go for your grid inspection. Thanks, todd Phone #: ###-#### Inspection requested via web by Todd Kurns. Needs electrical and mech. rough in inspections above grid first.
|
BLD-Other | 10/10/2019 | 10/17/2019 | 10/17/2019 | A | NR |
Mike Jordan
|
|
|
Ceiling Grid Inspection. Mike. Call me. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
BLD-Framing/Rough-in | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | PASS |
Mike Jordan
|
|
|
Contractor to remove screws as rock is being hung. Will check on grid inspection.
|
BLD-Framing/Rough-in | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | FAIL |
Mike Jordan
|
|
|
Mike,
Call me if you can''t get in. Thanks,
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns. Needs to remove all screws from top track to grid.
|
Issue PAID IN FULL permit | | | 7/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/24/2019 | 7/27/2019 | 7/25/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 7/25/2019 | | DONE |
|
|
|
ALL MET- NEED-
GC
Revised Certificate of Value
|
Routing - FIRE | 7/20/2019 | 7/20/2019 | 7/24/2019 | | PASS |
Mark Scharfen
|
|
|
07.24.2019-Completed fire review. Made notation on plans. No report (small TI).
|
Plan assigned to (JG) | 7/16/2019 | 7/16/2019 | 7/24/2019 | | PASS |
Javier Guzman
|
|
|
07/26 L2 ProTouch Home Cleaners #180 ePlan, pend fire
|
1st review completed | | | 7/24/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/16/2019 | | 7/23/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 7/16/2019 | | 7/17/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/16/2019 | | 7/16/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 7/16/2019 | | 7/16/2019 | | PASS |
Doug Chausow
|
|
|
Suite 180
|
Routing - PUBLIC WORKS | 7/16/2019 | | 7/16/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 7/16/2019 | | 7/16/2019 | | PASS |
Katelyn Menuge
|
|
|
Redline- New mechanical equipment shall be screened from public view.
|
Intake Approval | | | 7/15/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 6/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2019 1:46PM
|