Second Notice | | 9/30/2019 | 9/29/2019 | | DONE |
|
|
|
This permit finaled on the web by Paul Saucerman
|
First Notice | 8/19/2019 | 8/19/2019 | 9/20/2019 | | DONE |
Mike Jordan
|
|
|
mailed 9-23-19
|
BLD-Final | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | PASS |
Mike Jordan
|
|
|
Requested by Shane Treasure ###-#### Phone #: ###-#### Inspection requested via web by Shane Treasure
|
DOC - Permit Finaled | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications with this scope of work (A fire sprinkler head will need to be added under overhead door with next tenant, this is a vanilla space with no occupancy, overhead door will remain shut), no fire alarm modifications with this scope of work, no occupancy vanilla shell so no fire extinguishers. Final life fire safety inspection for scope of work complete.
Requested by Shane Treasure ###-#### Phone #: ###-#### Inspection requested via web by Shane Treasure
|
Letter of compliance/Occupancy | | | 8/19/2019 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PASS |
Mike Jordan
|
|
|
Request inspection of shear wall and hold downs. Shane Treasure ###-#### Phone #: ###-#### Inspection requested via web by Shane Treasure. Also reviewed special inspection report for the epoxy doweling.
|
Telephone call | | | 8/8/2019 | | DONE |
|
|
|
fees due were sent to brian@oaandd.com and chad@trekck.com
|
Issue PAID IN FULL permit | | | 8/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 7/12/2019 | 7/12/2019 | 7/31/2019 | | PASS |
Joe Bruce
|
|
|
08/02 (2nd Rev) 07/25 (L2) Mod Pizza Structural Upgrades, ePlan
|
Routing - PLAN CHECK | 7/31/2019 | | 7/31/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 7/31/2019 | | 7/31/2019 | | PASS |
Joe Bruce
|
|
|
AHJ - Chris H.
|
Plan resubmittals requested | | | 7/31/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/31/2019 | | DONE |
Joe Bruce
|
|
|
Spoke with Brian G. regarding the shear wall layout not matching the future MOD pizza shear wall layout. The interior shear wall is being restored to pre-existing condition. The shear wall will be modified under BLD19-02238 to match MOD pizza's floor plan layout.
|
Routing - PLAN CHECK | 7/31/2019 | | 7/31/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2019 | | DONE |
Joe Bruce
|
|
|
|
Permit Ready to Issue | | | 7/31/2019 | | DONE |
|
|
|
ALL MET-
NEED
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 7/24/2019 | 7/27/2019 | 7/25/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 7/12/2019 | | 7/24/2019 | | FAIL |
Joe Bruce
|
|
|
Revised structural drawings to be uploaded by applicant per CJW.
|
Routing Off Site - STRUCTURAL | 7/12/2019 | | 7/24/2019 | | PASS |
Joe Bruce
|
|
|
AHJ
|
Plan resubmittals requested | | | 7/24/2019 | | DONE |
Joe Bruce
|
|
|
|
1st review completed | | | 7/24/2019 | | FAIL |
Joe Bruce
|
|
|
|
Intake Approval | | | 7/11/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by BJM.
|
Intake Approval | | | 7/10/2019 | | FAIL |
Brian McGowan
|
|
|
Form #310 must be completed. Fill in Special Inspection Firm if known, Design Professional in Charge and the Owner Information. The owner must sign the document.
|
Intake Approval | | | 7/3/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following for your Prescreen to be approved;
1. The Submittal Checklist specifies a Site Plan on a1.11 - site Plan. Is there a Sheet a1.11? If so please upload it.
2. Verify if Special Inspections are required. (Post installed hold downs into exisitng concrete) Provide a completed Form #310 if so.
|
Application received | | | 7/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 2 2019 3:11PM
|