Third Notice | | 2/12/2020 | 2/12/2020 | | DONE |
|
|
|
This permit finaled on the web by Harvey Reyna
|
Second Notice | | 1/9/2020 | 2/7/2020 | | DONE |
|
|
|
mailed 2-10-20
|
First Notice | 12/5/2019 | 12/5/2019 | 12/30/2019 | | DONE |
Mike Jordan
|
|
|
mailed 1-1-20
|
BLD-Final | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Mike Jordan
|
|
|
Following is link to special inspection report for high strength bolting. https://pacificsource.egnyte.com/dl/L6ORwNt7Zw Not actively on site, if you could call atleast 30 minutes ahead of time, I can meet you there. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
DOC - Permit Finaled | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | PART |
Mike Jordan
|
|
|
Inspection requested via web by Scott Henderson. Will have special inspection on high strength bolting. All plys in contact.
|
BLD-Foundation | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Mike Jordan
|
|
|
On site contact is Robert. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Footing | 10/4/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Brandon Shaw
|
|
|
Project is behind secured gate. Work in progress...
|
BLD-Footing | 10/3/2019 | 10/4/2019 | 10/4/2019 | P | CANC |
Mike Jordan
|
|
|
Project is behind secured gate. If you could call 10 mins prior to arrival, I can meet you at gate, Scott. Phone #: ###-#### >> Inspection requested via web by Scott Henderson Inspection cancelled from web by: Scott Henderson
|
Issue PAID IN FULL permit | | | 9/30/2019 | | DONE |
|
|
|
emailed Scott Henderson to sign permit and send back
|
Print Occupancy Form | | | 9/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/30/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/27/2019 | | DONE |
|
|
|
emailed Scott Henderson that not all the fees were paid. I told him in the email once the fees qare paid, email permits@cityofboise.org so we all know those fees were paid
|
OVERRIDE | | | 9/18/2019 | | |
|
|
|
|
Plan assigned to (BJM) | 7/11/2019 | 7/11/2019 | 9/18/2019 | | DONE |
Brian McGowan
|
|
|
09/20- 502 Idaho Power Covered Parking Structure (NEED STRUCTURAL TO PASS)
|
Routing Off Site - STRUCTURAL | 9/18/2019 | | 9/18/2019 | | PASS |
Brian McGowan
|
|
|
See email from AHJ in Agency Documents
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/18/2019 | | DONE |
|
|
|
emailed Scott Henderson that all the fees were not paid
all met-NEED
ACHD-met
GC FORM -met
REVISED VALUE -met
emailed Scott Henderson the fees due
|
Routing Off Site - STRUCTURAL | 9/12/2019 | | 9/12/2019 | | FAIL |
Brian McGowan
|
|
|
See Structural Comment, not all items resolved.
|
Route to Impact Fee Review | 8/26/2019 | 8/29/2019 | 8/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/11/2019 | 7/11/2019 | 8/26/2019 | | PASS |
Mark Scharfen
|
|
|
Idaho Power Covered Parking Structure fire review completed 08.26.2019. No report needed. Fire department access/roads acceptable. U structure, no extinguishers required. Passed fire review.
|
Routing - PLAN CHECK | 7/11/2019 | | 8/26/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 8/26/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing Off Site - STRUCTURAL | 7/11/2019 | | 7/21/2019 | | FAIL |
Brian McGowan
|
|
|
AHJ
|
Routing - PLANNING | 7/11/2019 | | 7/17/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Design Review | 7/11/2019 | | 7/12/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00224
|
Routing - Addressing | 7/11/2019 | | 7/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/11/2019 | | 7/11/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 7/11/2019 | | 7/11/2019 | | PASS |
Michael Zawacki
|
|
|
|
Plan Reviewer's activity | | | 7/11/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 7/11/2019 | | PASS |
Carl Westfall
|
|
|
|
Routing PW Drainage | 7/11/2019 | | 7/11/2019 | | PASS |
Brian Murphy
|
|
|
LESS THAN 1000 SQURE FEET
|
Routing PW Street Lights | 7/11/2019 | | 7/11/2019 | | PASS |
Tom Marshall
|
|
|
|
Application received | | | 7/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 10 2019 9:38AM
|