BLD-Final | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PASS |
Dave Hannah
|
|
|
Joshua Phone #: ###-####
|
DOC - Permit Finaled | 2/21/2020 | 2/21/2020 | 2/21/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | PASS |
Jim Storey
|
|
|
Josua Phone #: ###-####
|
BLD-Framing/Rough-in | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Dave Hannah
|
|
|
josh Phone #: ###-####
|
BLD-Wall Bracing | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Dave Hannah
|
|
|
shear // Josh Phone #: ###-####
|
BLD-Foundation | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | DONE |
Tell Riley
|
|
|
Brandon- Concrete at 1:30 footing foundation Phone #: ###-####//no property pins were present//contractor is pouring footings at his own risk--unable to call off concrete//pins need to be set and setbacks verified prior to going vertical//
|
OVERRIDE | | | 7/29/2019 | | |
|
|
|
|
Telephone call | | | 7/29/2019 | | DONE |
|
|
|
spoke with josh informing him that this permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 7/29/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 7/10/2019 | | 7/29/2019 | | PASS |
Josh Bogle
|
|
|
07/23 ADU, paper - 1st done
|
Routing - PLAN CHECK | 7/29/2019 | | 7/29/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 7/29/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/29/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 7/29/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/23/2019 | | DONE |
|
|
|
Two whole new set of plans to scale stamped and taken to Josh B
|
1st review completed | | | 7/17/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/12/2019 | | 7/17/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Josh
|
Routing - MECHANICAL | 7/10/2019 | | 7/12/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 7/10/2019 | 7/13/2019 | 7/11/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 7/10/2019 | | 7/11/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2019 | | 7/11/2019 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 7/10/2019 | 7/15/2019 | 7/10/2019 | | PASS |
Shannon Cade
|
|
|
|
Routing - Addressing | 7/10/2019 | | 7/10/2019 | | PASS |
Doug Chausow
|
|
|
ADU address: 2529 W Davis St
|
Intake Approval | | | 7/10/2019 | | FAIL |
|
|
|
NEED
WALL INSTALLATION
ANCHOR BOLTS
|
Plans ACCEPTED BY PLAN TECH | | | 7/10/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/10/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/10/2019 | | PASS |
|
|
|
|
Application received | | 7/10/2019 | | | |
|
|
|
|