Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-02584
StatusIssued
Name ROCKY MOUNTAIN REMODELING INC
Site Address 12033 W FLORIDA DR
Project NameBooth piers
Customer Number 
ePlanReviewYes
Description
SPECIAL INSPECTIONS REQUIRED - Permit to add six push piers to shore up an existing foundation. All work per plans, attachments, engineering, local codes & ordinances. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Footing8/23/20198/26/20198/26/2019APEND
DetailsMike Jordan
Will send special inspection report once we get from ABCO Phone #: ###-#### Inspection requested via web by Cassandra Hessing. Anchors are installed. Will final project once backfill i completed and special inspection report has been recieved noting that work was in complaince with approved plans and engineering.
Issue PAID IN FULL permit  8/12/2019 DONE
Inspection Record Card- Bld  8/12/2019 DONE
Plan assigned to (JAB) Josh7/26/20197/26/20198/2/2019 PASS
DetailsJosh Bogle
08/01 piers, ePlan
Routing - PLAN CHECK7/26/2019 8/2/2019 PASS
DetailsJosh Bogle
Routing - PLANNING7/26/2019 8/2/2019 PASS
DetailsSue Cummings
1st review completed  8/2/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  8/2/2019 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  8/2/2019 DONE
Routing PW Flood Plain7/26/2019 7/29/2019 PASS
DetailsJason C. Taylor
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
Plans ACCEPTED BY PLAN TECH  7/26/2019 DONE
Intake Approval  7/26/2019 PASS
Recd Pcfee & Taken To Pln CK  7/26/2019 DONE
Intake Approval  7/18/2019 FAIL
1. Recorded Site Plan of whole property-Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines. Indicate bearings, distance, and curve data in conformance with the recorded plat. Show any easement locations- (per Planner J.L.)
2.Elevation Certificate (For structures located in Floodplain only).
Intake Approval  7/17/2019 FAIL
Drawings must be uploaded in proper orientation (landscape)
Application received  7/12/2019 DONE
Application submitted via PDS Online on Jul 12 2019 10:43AM