BLD-Footing | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PEND |
Mike Jordan
|
|
|
Will send special inspection report once we get from ABCO Phone #: ###-#### Inspection requested via web by Cassandra Hessing. Anchors are installed. Will final project once backfill i completed and special inspection report has been recieved noting that work was in complaince with approved plans and engineering.
|
Issue PAID IN FULL permit | | | 8/12/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 7/26/2019 | 7/26/2019 | 8/2/2019 | | PASS |
Josh Bogle
|
|
|
08/01 piers, ePlan
|
Routing - PLAN CHECK | 7/26/2019 | | 8/2/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 7/26/2019 | | 8/2/2019 | | PASS |
Sue Cummings
|
|
|
|
1st review completed | | | 8/2/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 8/2/2019 | | DONE |
|
|
|
|
Routing PW Flood Plain | 7/26/2019 | | 7/29/2019 | | PASS |
Jason C. Taylor
|
|
|
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/26/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2019 | | FAIL |
|
|
|
1. Recorded Site Plan of whole property-Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines. Indicate bearings, distance, and curve data in conformance with the recorded plat. Show any easement locations- (per Planner J.L.)
2.Elevation Certificate (For structures located in Floodplain only).
|
Intake Approval | | | 7/17/2019 | | FAIL |
|
|
|
Drawings must be uploaded in proper orientation (landscape)
|
Application received | | | 7/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 12 2019 10:43AM
|