Permanent Occupancy | | | 11/19/2019 | | DONE |
|
|
|
|
BLD-Aging Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | | PASS |
Tell Riley
|
|
|
needs plumbing final for grease trap//
|
Temporary Occupancy | 8/23/2019 | 11/21/2019 | 8/23/2019 | | DONE |
Gemma Flores
|
|
|
|
BLD-Final | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Tell Riley
|
|
|
Tasmyn-please call prior to meet for access Phone #: ###-####//occupancy ok per plans when plumbing final is complete//temp ok until then//
|
FIRE-Final Inspection | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the fire extingusher.
call to meet // tasmyn Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/21/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 7/12/2019 | 7/12/2019 | 8/20/2019 | | PASS |
Joe Bruce
|
|
|
(1st Rev Comp) 07/19 (528) Moss Coffee & Tea, Paper
|
Plan resubmittals received | | | 8/20/2019 | | DONE |
Joe Bruce
|
|
|
Received email from Tasmyn with CDHD approval.
|
Routing - PLAN CHECK | 8/20/2019 | | 8/20/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/20/2019 | | DONE |
Joe Bruce
|
|
|
|
Permit Ready to Issue | | | 8/20/2019 | | DONE |
|
|
|
met
|
Print Occupancy Form | | | 8/20/2019 | | DONE |
|
|
|
|
Telephone call | | | 8/20/2019 | | DONE |
|
|
|
Spoke with Tasmyn to inform them the permit is ready to pick up.
|
1st review completed | | | 7/18/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 7/15/2019 | | 7/18/2019 | | FAIL |
Joe Bruce
|
|
|
Need CDHD approval prior to issuing permit.
|
Plan Reviewer's activity | | | 7/16/2019 | | DONE |
Joe Bruce
|
|
|
Spoke with applicant on the phone regarding the passive grease trap required to be installed along with providing CDHD approval prior to issuing permit. **JHB**
|
Routing - Addressing | 7/12/2019 | | 7/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 7/15/2019 | | PASS |
|
|
|
|
Routing - PLANNING | 7/15/2019 | | 7/15/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing PW Environmental | 7/15/2019 | | 7/15/2019 | | PASS |
Rick Christenson
|
|
|
Passive Grease Trap to be installed.
|
Intake Approval | | | 7/12/2019 | | PASS |
Joe Bruce
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/12/2019 | | DONE |
|
|
|
|
Application received | | 7/12/2019 | | | |
|
|
|
|