Print Statement | | | 1/22/2020 | | DONE |
|
|
|
SECOND PAST DUE NOTICE
|
Print Statement | | | 1/8/2020 | | DONE |
|
|
|
|
Print Statement | | | 12/11/2019 | | DONE |
|
|
|
|
BLD-Final | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####
|
Permanent Occupancy | | | 11/1/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The building inspector is going to verify the door hardware on the office.
Dave Phone #: ###-####
|
FIRE-Final Inspection | 10/16/2019 | 10/17/2019 | 10/17/2019 | P | FAIL |
Troy Cobbley
|
|
|
*** FAIL No ceiling tiles installed. Fire sprinklers not installed in tiles. Duct wrap needs repaired in 2 places where sitting on grid. MAS***
Dave Phone #: ###-####
|
BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 | A | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####,, grid ok
|
Print Occupancy Form | | | 9/9/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/9/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/29/2019 | 9/1/2019 | 8/29/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 8/23/2019 | 8/23/2019 | 8/29/2019 | | PASS |
Javier Guzman
|
|
|
08/28 L1 >U.S Bank albertsons ePlan*
|
Routing - PLAN CHECK | 8/23/2019 | | 8/29/2019 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 8/29/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/29/2019 | | DONE |
|
|
|
MET CHRISL@RADIXCONTRUCTION.COM
Need GC Form and Revised Value
|
Routing - Addressing | 8/23/2019 | | 8/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/23/2019 | | 8/23/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Routing - Design Review | 8/23/2019 | | 8/23/2019 | | PASS |
KayCee Babb
|
|
|
No exterior alterations are proposed. No additioanl Design Review is required***Sent to DR because it seems like exterior wall is being infilled but Brian McGowen spoke with applicant and they said it is not the exterior wall
|
Intake Approval | | | 8/22/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 8/14/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following in order for your Prescreen to be approved:
1. Every Plan Sheet must provide an area in the bottom right hand corner for the City Approved Stamp. See requirements with uploading Documents in ePlan.
2. Provide a completed form 304.
3. Show Exit and emergency lighting for the Tenant Space.
4. Please provide a more clarifying Key Plan. It appears you may be modifying the exterior of the building. If so, Planning and Zoning approval letters are required as well as further details, sections etc.
|
Intake Approval | | | 7/16/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following in order for your Prescreen to be approved:
1. Provide a completed Submittal Checklist and all forms, documents and drawings as required.
2. Every Plan Sheet must provide an area in the bottom right hand corner for the City Approved Stamp. See requirements with uploading Documents in ePlan.
|
Application received | | | 7/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2019 9:51AM
|