Second Notice | | 3/15/2020 | 3/12/2020 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | | 2/23/2020 | 3/5/2020 | | DONE |
|
|
|
mailed 3-6-20
|
BLD-Final | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | PASS |
Mike Jordan
|
|
|
tim Phone #: ###-####
|
FIRE-Final Inspection | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Tim Phone #: ###-####
|
Permanent Occupancy | | | 2/13/2020 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Mike Jordan
|
|
|
Tim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | NR |
Tell Riley
|
|
|
Steve Phone #: ###-####//need mechanical inspection//add wire to light in office//maintain fire wall//
|
BLD-Framing/Rough-in | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PASS |
Mike Jordan
|
|
|
Tim Phone #: ###-####. Interior steel stud framed walls only ok.
|
Permit Ready to Issue | | | 12/12/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 12/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 12/3/2019 | 12/3/2019 | 12/11/2019 | | DONE |
Julie Romig
|
|
|
12/16 - Plan Mod GSA Law Enforcement
|
Routing - PLAN CHECK | 12/4/2019 | | 12/11/2019 | | PASS |
Julie Romig
|
|
|
|
Plan Modification Accepted | | | 12/3/2019 | | DONE |
|
|
|
Adrienne Lane-Martin from erstad Architects requested a plan mod workflow. Revise door layout in 2 rooms, revise wall type, revise lighting layout in one room. Sheets a2.01, a2.11, a2.31, a6.11, e1.0, e2.0
|
Print Occupancy Form | | | 12/2/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/2/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/2/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/22/2019 | 7/22/2019 | 8/15/2019 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - L2 GSA Law Enforcement
|
Routing - MECHANICAL | 7/22/2019 | | 8/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/15/2019 | | 8/15/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/15/2019 | | DONE |
|
|
|
ALL MET (office@ekcconstruction.com) (Adrienne@erstadarchitects.com)
Need GC
Need Rev Val
|
Route to Impact Fee Review | 8/8/2019 | 8/11/2019 | 8/9/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/8/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/22/2019 | | 8/8/2019 | | FAIL |
Julie Romig
|
|
|
|
Intake Approval | | | 7/22/2019 | | PASS |
Julie Romig
|
|
|
Prescreen approved by JAR.
|
Routing - Addressing | 7/22/2019 | | 7/22/2019 | | PASS |
Doug Chausow
|
|
|
Ste 101
|
Routing - PUBLIC WORKS | 7/22/2019 | | 7/22/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Intake Approval | | | 7/19/2019 | | FAIL |
Julie Romig
|
|
|
Need blank stamping space on a6.11 and e0.0
|
Application received | | | 7/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 16 2019 3:53PM
|