Permit Information
Permit NumberBLD19-02656
StatusFinaled
Name BILTMORE COMPANY
Site Address 11716 W FAIRVIEW AVE
Project NameFairview Apartments carport
Customer Number 
ePlanReviewYes
Description
(FAIRVIEW APARTMENT CARPORTS) Permit to construct 18 seperate all steel carports. (3) 8-bay carports approximately 1136 sqft, (6) 6-bay carports approximately 848 sqft, (2) 5-bay carports approximately 688 sqft, and (7) 4-bay carports approximately 544 sqft. Total carport area is 13,680 sqft. and the carports will cover (2) accessible parking spots. Work to include footings, columns, roof structure, and signage. These carports are not fire sprinklered. All work to comply with applicable codes and attached engineeering. **MDH**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/4/20201/10/2020 DONE
This permit finaled on the web by Jeremy Amar
Second Notice 12/5/201912/30/2019 DONE
mailed 1-1-20
First Notice 11/3/201911/25/2019 DONE
mailed 12-2-19
Permanent Occupancy  10/24/2019 DONE
BLD-Final10/22/201910/22/201910/22/2019PPASS
DetailsTell Riley
Matt Phone #: ###-####//engineer provided letter for bracing//final complete//signed card//
BLD-Final10/21/201910/21/201910/22/2019PNR
DetailsTell Riley
Pat Phone #: ###-####//need clarification on purlin supports shown in details on plans//
FIRE-Final Inspection10/18/201910/21/201910/21/2019APASS
DetailsTroy Cobbley
Life safety passed. Per Boise City addressing dept the project address is not an issue.

Matt Phone #: ###-####
Zoning Approval10/18/201910/18/201910/18/2019 DONE
DetailsKatelyn Menuge
Zoning Inspection not Required for Carports
BLD-Footing10/14/201910/15/201910/15/2019APASS
DetailsTell Riley
as early as possible... north half // Pat Phone #: ###-####//2nd and last for canopies// fooitngs per engineering//ok pending any special inspection requirements//
PubWorks Occupancy Approval10/14/201910/14/201910/14/2019 DONE
DetailsTiffany Lowery
BLD-Footing10/9/201910/10/201910/10/2019APART
DetailsTell Riley
Pat Phone #: ###-####//ok pending any special inspections that may be required//first half of covers//
Issue PAID IN FULL permit  10/4/2019 DONE
Print Occupancy Form  10/4/2019 DONE
OVERRIDE  10/3/2019  
Routing PW Street Lights10/2/2019 10/3/2019 PASS
DetailsTom Marshall
Routing - PLAN CHECK10/3/2019 10/3/2019 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  10/3/2019 DONE
Permit Ready to Issue  10/3/2019 DONE
met: sheryl@biltmoreco.com

Need GC
Plan assigned to (M_H)8/15/2019 10/3/2019 DONE
DetailsMichael Hanson
1st review completed - 09/25 #502 L3 ePlan - Fairview Apts Carports
Route to Impact Fee Review9/27/20199/30/201910/2/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - Design Review10/1/2019 10/1/2019 PASS
DetailsKatelyn Menuge
Redlined DR requirement for finish/color.
Routing - PLANNING10/1/2019 10/1/2019 PASS
DetailsDavid Moser
The PUD noted a 15 foot street side setback and approved site plan showed parking with reduced setbacks
1st review completed  9/27/2019 DONE
DetailsMichael Hanson
Routing - PLANNING9/27/2019 9/27/2019 FAIL
DetailsDavid Moser
The carports do not comply with setbacks from King Street
Routing - FIRE8/15/20198/20/20199/26/2019 PASS
DetailsMark Stumbaugh
09/25 - 502 Fairview Apts Carports
Routing Off Site - STRUCTURAL8/20/2019 9/25/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required per C. Holliday @ AHJ engineering.
Routing - PLAN CHECK8/15/2019 9/25/2019 FAIL
DetailsMichael Hanson
See comments from other departments. Building review will occur when final locations of carports are completed and approved by design review and planning.
Routing PW Sewer Design8/21/2019 8/26/2019 PASS
DetailsDeAnn Brown
No new sewer work proposed.
Routing PW Street Lights8/21/2019 8/23/2019 PASS
DetailsTom Marshall
Routing PW Solid Waste8/21/2019 8/23/2019 PASS
DetailsEvan Carpenter
Routing PW Drainage8/21/2019 8/21/2019 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS8/20/2019 8/21/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment8/20/2019 8/21/2019 PASS
DetailsMichael Zawacki
Routing - PLANNING8/20/2019 8/20/2019 FAIL
DetailsDavid Moser
Carports were not included with PUD17-00022 approval and adding carports requires a PUD modification application and it also requires design review approval.
Routing - Addressing8/20/2019 8/20/2019 PASS
DetailsLaura Hunter
Routing - Design Review8/20/2019 8/20/2019 FAIL
DetailsAndrea Tuning
The proposed 8 space carport adjacent to the open space with the gazebo is located within the street side setback.

The applicant was also required to submit a site plan and elevations for carports within the development to Design Review for review and approval. This was never completed.
Intake Approval  8/15/2019 PASS
DetailsJulie Romig
Intake Approval  8/8/2019 FAIL
DetailsJulie Romig
After discussion with Jim Escobar, it appears that the stamped/signed architectural sheets were submitted prematurely, with Jim's redlines rather than final updates. I've sent the prescreen task back to you so you can update the final stamped/signed architectural sheets.
Intake Approval  7/18/2019 FAIL
DetailsJulie Romig
1. Leave a 4" x 2" blank space on each sheet in the lower right hand corner, located 3" off the sheet edge for the City of Boise permit stamp. On the cover sheet, leave a blank 4" x 4" blank space in this location.
2. The cover sheet is for the Fairview Apartments and does not include a code analysis specific to the carports. Please provide a cover sheet for the carports with code analysis including the carport construction type, occupancy, occupant load, square footage and whether the carports are sprinklered.
Application received  7/17/2019 DONE
Application submitted via PDS Online on Jul 17 2019 9:02AM