BLD-Final | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Tony Young
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk
|
DOC - Permit Finaled | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Tony Young
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk// 3.3
|
PubWorks Occupancy Approval | 7/23/2020 | 7/23/2020 | 7/23/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer/landscape architect indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Aging Inspection | 4/29/2020 | 4/29/2020 | 4/30/2020 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/30/2020 | 4/30/2020 | 4/30/2020 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 12/13/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Dave Hannah
|
|
|
Insulation inspection. Thank you! Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | PASS |
Tony Young
|
|
|
Framing inspection. Thank you. Phone #: ###-#### Inspection requested via web by Clayton Conner// fireplace is on main mech permit// ok to insulate
|
BLD-Framing/Rough-in | 10/30/2019 | 10/31/2019 | 10/31/2019 | A | PART |
Tony Young
|
|
|
Shear Wall inspection. Thank you Phone #: ###-#### Inspection requested via web by Clayton Conner// shear ok
|
BLD-Foundation | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PART |
Tony Young
|
|
|
Edgar Phone #: ###-####,, ok,, will get footing protection before final
|
PubWorks Subgrade Approval | 9/5/2019 | 9/5/2019 | 9/5/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 8/28/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/28/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/26/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 7/23/2019 | 7/23/2019 | 8/26/2019 | | DONE |
Rob Patrick
|
|
|
08/09 sfd L2 ePlan...08/08 Failed...08/13 Review complete all good; waiting for Melissa
|
Routing - PLAN CHECK | 8/26/2019 | | 8/26/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/26/2019 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 8/22/2019 | | 8/22/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
1st review completed | | | 8/8/2019 | | FAIL |
Rob Patrick
|
|
|
Melissa requires corrections. Bldg review complete, all good.
|
Routing - PLAN CHECK | 7/23/2019 | | 8/8/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing PW Grading-Hillside | 7/23/2019 | | 7/29/2019 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in ePlan
|
Route to Impact Fee Review | 7/23/2019 | 7/26/2019 | 7/24/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/23/2019 | | 7/24/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/23/2019 | | 7/24/2019 | | PASS |
Karla Nelson
|
|
|
Plans match hillside approval for planning.
|
Routing - FIRE | 7/23/2019 | 7/23/2019 | 7/23/2019 | | PASS |
Lee G Meredith
|
|
|
08/05 3809 E Sandpoint Way-Res ePlan
Sprinklers are not required.
|
Plans ACCEPTED BY PLAN TECH | | | 7/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/23/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/23/2019 | | DONE |
|
|
|
|
Routing - Addressing | 7/23/2019 | | 7/23/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address: 3809 N Sandpoint Way
|
Routing - PUBLIC WORKS | 7/23/2019 | | 7/23/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 7/23/2019 | | 7/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site preparation inspection
|
Application received | | | 7/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2019 12:23PM
|