BLD-Conference | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | DONE |
Tell Riley
|
|
|
Pete Stewart desires a consulting framing inspection Phone #: ###-#### Inspection requested via web by Peter Stewart
|
CHANGE STATUS TO (ISS) | | | 7/9/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 7/8/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 6/25/2020 | 6/25/2020 | 7/8/2020 | | DONE |
Jenny Nelson
|
|
|
plan mod - paper to ePlan
|
Routing - PLAN CHECK | 7/6/2020 | | 7/8/2020 | | PASS |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 7/8/2020 | | DONE |
|
|
|
Plan Mod Do Not Reissue * MET
|
Telephone call | | | 6/25/2020 | | DONE |
|
|
|
Called and left applicant a voicemail to let them know they need only upload plan mod sheets in their ePlan
|
Plan Modification Accepted | | | 6/24/2020 | | DONE |
|
|
|
Peter Stewart has requested a plan mod for modification on the garage wall.
|
BLD-Aging Inspection | 6/19/2020 | 6/19/2020 | 6/23/2020 | | CANC |
Tell Riley
|
|
|
|
BLD-Aging Inspection | 6/18/2020 | 6/18/2020 | 6/19/2020 | | PASS |
Tell Riley
|
|
|
met with Pete last week on a conference//WIP//shear walls and roof will be completed soon//
|
BLD-Conference | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | DONE |
Tell Riley
|
|
|
Screened- please call if possible-Stewert Phone #: ###-####//shear questions//
|
Inspection Record Card- Bld | | | 5/29/2020 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/5/2020 | 2/5/2020 | 2/5/2020 | | PASS |
Tell Riley
|
|
|
WIP
|
BLD-Foundation | 9/19/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Peter Stewart
|
BLD-Footing | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Tell Riley
|
|
|
concrete at 11am // Peter Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/10/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/9/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 9/5/2019 | 9/5/2019 | 9/9/2019 | | DONE |
Jenny Nelson
|
|
|
plan mod #1 2 large plans that reposition the under floor pony walls to reduce span distances.
|
Routing - PLAN CHECK | 9/9/2019 | | 9/9/2019 | | PASS |
Jenny Nelson
|
|
|
Plan modification
|
Case Summary (BLD) | | | 9/9/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 9/9/2019 | | DONE |
|
|
|
plan mod approved
|
Telephone call | | | 9/9/2019 | | DONE |
|
|
|
Left voicemail for Peter to inform him the plan mod is ready and what fees are due.
|
Plan Modification Accepted | | | 9/5/2019 | | DONE |
|
|
|
plan mod #1 2 large plans that reposition the under floor pony walls to reduce span distances.
|
Plan Reviewer's activity | | | 9/4/2019 | | DONE |
Michael Hanson
|
|
|
Discussed the requirements for a plan mod in regards to the foundation changes the applicant would like to make. Applicant would like to go from 16x12 footing to 16x8 footing. Plan mod required.
|
Issue PAID IN FULL permit | | | 8/8/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 7/18/2019 | 7/18/2019 | 7/24/2019 | | DONE |
Jenny Nelson
|
|
|
07/31 sfd L1 Paper
|
Routing - PLAN CHECK | 7/23/2019 | | 7/24/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 7/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
Inspection Record Card- Bld | | | 7/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/24/2019 | | DONE |
|
|
|
Met
(if parcel owner not GC 302 form needs to be filled out and RP needed)
|
Telephone call | | | 7/24/2019 | | DONE |
|
|
|
cleft message on ###-#### owner to inform him fees due and if GC is picking this up we will need RP
|
1st review completed | | | 7/24/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 7/19/2019 | | 7/23/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 7/18/2019 | 7/21/2019 | 7/19/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 7/19/2019 | | 7/19/2019 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 7/18/2019 | | 7/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/18/2019 | | 7/19/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2019 | | DONE |
|
|
|
|
Application received | | 7/18/2019 | | | |
|
|
|
|