BLD-Final | 5/22/2020 | 5/27/2020 | 5/27/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/22/2020 | 5/27/2020 | 5/27/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4 ,2
|
BLD-Blower Door Test Results | 5/19/2020 | 5/26/2020 | 5/22/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Final | 5/19/2020 | 5/26/2020 | 5/22/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Energy code compliance | 3/18/2020 | 3/24/2020 | 3/24/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 3/18/2020 | 3/20/2020 | 3/20/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
Brandon Shaw
|
|
|
shear // Eber Phone #: ###-####
|
BLD-Foundation | 1/2/2020 | 1/2/2020 | 1/2/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Edgar Sanchez
|
BLD-Footing | 12/30/2019 | 12/30/2019 | 12/30/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Edgar Sanchez Inspection cancelled from web by: Edgar Sanchez
|
BLD-Footing | 12/19/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Edgar Sanchez
|
PubWorks Subgrade Approval | 12/19/2019 | 12/19/2019 | 12/19/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 11/15/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/26/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 7/19/2019 | 7/19/2019 | 8/26/2019 | | DONE |
Rob Patrick
|
|
|
08/01 sfd L1 ePlan...08/01 Failed...08/21 waiting on email clarification from Amy
|
Routing - PLAN CHECK | 8/26/2019 | | 8/26/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 8/26/2019 | | DONE |
|
|
|
|
1st review completed | | | 8/1/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 7/19/2019 | | 8/1/2019 | | FAIL |
Rob Patrick
|
|
|
|
Route to Impact Fee Review | 7/19/2019 | 7/22/2019 | 7/22/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 7/19/2019 | 7/19/2019 | 7/19/2019 | | PASS |
Lee G Meredith
|
|
|
Sprinklers are not required.
|
Routing - MECHANICAL | 7/19/2019 | | 7/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/19/2019 | | 7/19/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 7/19/2019 | | 7/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/19/2019 | | 7/19/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/19/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 7/19/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2019 | | DONE |
|
|
|
|
Application received | | | 7/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2019 3:08PM
|